The global AI buildout

Today Nov 2026

19.5GW of power capacity at the tracked AI campuses

the power capacity of the 96 large AI campuses that Epoch AI tracks, about 44% of the world's AI computing capacity

At full load, the power of 16.2 million US homes.

Online
76
Building
20
Data-centre power use, 2025
485 TWh
World AI compute, Q2 2026
31.7M H100e
Share at these campuses, Epoch’s estimate
about 44%
Capex, Q3 2026
$265.5B
Cloud regions
297 in 46 countries

Data: Epoch AI, CC BY 4.0 · IEA, CC BY 4.0 · company filings · cloud providers · by country · sources

A globe of the global AI buildout. Each light is one large AI campus, its area the campus's power; rings are AI supercomputers and small squares are public cloud regions.
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

On a light page, end the frame’s address with ?theme=light. Preview it light.

Cite
Download
Post on X

The tracked AI campuses have added 1.3 GW since 22 Oct 2026

Epoch's 22 Oct 2026 release against 13 Nov 2026
  1. Switched on6 sites +803 MW
  2. 22 Oct 2026, restated3 sites revised by Epoch +296 MW
  3. Newly tracked1 site +155 MW
  4. Net change18.2 GW → 19.5 GW +1,254 MW
Facility power of the tracked sites went from 18.2 GW in Epoch's 22 Oct 2026 release to 19.5 GW on 13 Nov 2026: +803 MW switched on in between, +296 MW from Epoch restating its 22 Oct 2026 figures, and +155 MW from newly tracked sites.

Switched on · 6

  1. OpenAI Stargate Abilene +289 MW 865 MW → 1.2 GW
  2. Anthropic Lake Mariner +196 MW 49 MW → 245 MW
  3. Envision Galaxy Ulanqab +153 MW 0 MW → 153 MW
  4. Meta Aiken +78 MW 90 MW → 168 MW
  5. Huawei Wuhu +54 MW 202 MW → 256 MW
  6. Meta Los Lunas +33 MW 114 MW → 147 MW

Restated · 3

  1. OpenAI Stargate Abilene +275 MW 590 MW → 865 MW
  2. Huawei Wuhu +21 MW 181 MW → 202 MW
  3. Huawei Horinger 0 MW 212 MW → 212 MW

Newly tracked · 1

  1. YTL Johor 155 MW Undisclosed
Sites tracked
95 → 96
Drawing power
74 → 76
Projected, Jan 2030
49.9 GW → 50.4 GW

Against Epoch's release of 22 Oct 2026 (archived copy).

10 of 94 planned campus power increases have slipped or shrunk

Each planned step against the newest release
On plan
84 steps · 27.3 GW planned · at the planned size on the planned date
Later
7 steps · 1.3 GW planned · the planned size, on a later date
Smaller
3 steps · 2.9 GW planned · never at the planned size

The IEA expects data centers to use 950 TWh by 2030

all data centers, worldwide · IEA
2024
415 TWh
2025
485 TWh
2030 · base case
950 TWh

about 1.5% of world electricity in 2024, and around 3% by 2030. AI-focused data centers reach about 465 TWh in 2030. IEA, CC BY 4.0.

By region, 2024

  1. United States more than 4% 180 TWh
  2. China 100 TWh
  3. Europe slightly less than 2% 70 TWh
  4. Japan about 2% <20 TWh
  5. India about 0.5% 9 TWh

$265.5B of capital spending in Q3 2026, up 127% on a year earlier

10 companies · quarterly
  1. $51.6B 2024 Q1
  2. $60.8B 2024 Q2
  3. $66.9B 2024 Q3
  4. $90.2B 2024 Q4
  5. $86.6B 2025 Q1
  6. $109.4B 2025 Q2
  7. $116.8B 2025 Q3
  8. $143.9B 2025 Q4
  9. $168.6B 2026 Q1
  10. $214.0B 2026 Q2
  11. $265.5B 2026 Q3
CompanyQ3 2026A year earlierChange
Amazon US $77.3B $35.1B +120%
Alphabet US $51.4B $24.0B +114%
Microsoft US $39.4B $19.4B +103%
Meta US $33.9B $18.8B +80%
Oracle US $28.5B $8.5B +235%
Tencent CN $9.7B $2.8B +246%
CoreWeave US $9.4B $2.4B +295%
Alibaba CN $7.5B $4.4B +70%
Nebius NL $7.3B $1.0B +664%
Baidu CN $1.1B $0.5B +129%

Cash spent on property and equipment, from each company's filings, in US dollars. The last four quarters total $792.0B.

54 countries

Every country →
Country Tracked campuses, today Their AI compute, H100e Cloud regions
United States 16.2 GW 13.6M 52
Malaysia 1.7 GW 1.4M 6
China 1.1 GW 336K 34
United Kingdom 124 MW 124K 10
Indonesia 94 MW 84K 7
Finland 90 MW 49K 2
Australia 57 MW 46K 10
Norway 55 MW 51K 1
Portugal 40 MW 32K —
Iceland 7 MW 6K —
Germany — — 8
Japan — — 13
France — — 9
Switzerland — — 4
Saudi Arabia — — 5

A dash means Epoch AI tracks no campus there, not that the country has none. Epoch AI estimates that its sites hold about 44% of the world’s AI computing capacity, and it covered the United States first.

Cloud regions by provider, live and open to all customers

  1. Microsoft Azure 49
  2. Oracle Cloud Infrastructure 45
  3. Google Cloud 43
  4. AWS 34
  5. Huawei Cloud 32
  6. Alibaba Cloud 30
  7. Tencent Cloud 21
  8. CoreWeave 21
  9. IBM Cloud 13
  10. Nebius 9

Brazil's Scala AI City leads the announced campuses at 4.75 GW

not tracked by Epoch AI · not in any total on this page
  1. Brazil · Scala AI CityScala Data Centers, Eldorado do Sul, Rio Grande do Sul 4.75 GWfull build, May 2025 · release
  2. Saudi Arabia · DataVolt OxagonDataVolt, Oxagon, NEOM 1.5 GWfull build, Aug 2026 · release
  3. France · Campus IAMGX, Bpifrance, Mistral AI and NVIDIA, Paris region 1.4 GWfull build, May 2025 · release
  4. Japan · SoftBank SakaiSoftBank, Sakai, Osaka over 400 MWfull build, Jun 2024 · release
  5. Germany · Schwarz Digits LübbenauSchwarz Digits, Lübbenau, Brandenburg around 200 MWfirst build, Nov 2025 · release

Each figure is the release's own, and the outline means announced, not built. None of these sites is in the tracked totals above. 3 of them are dashed rings on the globe, at the town the release names. DataVolt Oxagon is not drawn: OpenStreetMap has no town named Oxagon, and NEOM is a region. Campus IA is not drawn: its release names the Paris region and no town.

From 82 MW in 2023 to 19.5 GW today

facility power of the tracked sites · by month

Epoch AI tracks sites that started to operate in 2024 or later, with some exceptions, so the early years hold few sites.

Jan 2023
82 MW
Today
19.5 GW
Jan 2030 · projected
50.4 GW
As a table
1 JanuaryFacility powerH100-equivalentsCapital costSites drawing power
2022 57 MW 8K $1.8B 1
2023 82 MW 14K $2.5B 2
2024 591 MW 213K $17.8B 7
2025 2.6 GW 1.2M $78.0B 23
2026 8.6 GW 5.9M $256.0B 47
2027 (projected) 22.1 GW 18.6M $647.0B 84
2028 (projected) 37.2 GW 41.0M $1.07T 92
2029 (projected) 50.2 GW 66.1M $1.45T 96
2030 (projected) 50.4 GW 66.2M $1.46T 96

The largest, today

by facility power

Today Projected peak

  1. 01 Colossus 2 SpaceXAI · Memphis, Tennessee 1.3 GW → 2.1 GW
  2. 02 Anthropic-Amazon New Carlisle Amazon · New Carlisle, Indiana 1.2 GW → 2.3 GW
  3. 03 OpenAI Stargate Abilene Oracle · Abilene, Texas 1.2 GW
  4. 04 Microsoft Fairwater Atlanta Microsoft · Fayetteville, Georgia 859 MW
  5. 05 DayOne Nusajaya Undisclosed · Johor Bahru, Johor, Malaysia 662 MW
  6. 06 Meta Prometheus Meta · New Albany, Ohio 612 MW → 1.3 GW
  7. 07 DayOne Kempas Undisclosed · Kempas, Johor, Malaysia 590 MW
  8. 08 Microsoft Fairwater Wisconsin Microsoft · Mount Pleasant, Wisconsin 442 MW → 2.7 GW
  9. 09 Google Pryor (North) Google · Pryor, Oklahoma 442 MW
  10. 10 Colossus 1 SpaceXAI · Memphis, Tennessee 425 MW → 442 MW
  11. 11 Google New Albany Google · New Albany, Ohio 400 MW
  12. 12 CoreWeave Denton TX CoreWeave · Denton, Texas 367 MW → 395 MW
  13. 13 Google Columbus Google · Columbus, Ohio 364 MW → 464 MW
  14. 14 Amazon Madison Mega Site Amazon · Canton, Mississippi 341 MW → 819 MW
  15. 15 QTS Richmond 1 Undisclosed · Sandston, Virginia 333 MW

The United States holds 83% of the tracked campuses' power

facility power today · 96 tracked sites

By owner

  1. Google 3.9 GW
  2. Meta 3.1 GW
  3. Undisclosed 2.6 GW
  4. Amazon 2.3 GW
  5. Microsoft 2.0 GW
  6. SpaceXAI 1.7 GW
  7. Oracle 1.2 GW
  8. CoreWeave 955 MW
  9. Huawei 468 MW
  10. ByteDance 315 MW
  11. 7 others 1.0 GW

By country

  1. United States 16.2 GW
  2. Malaysia 1.7 GW
  3. China 1.1 GW
  4. United Kingdom 124 MW
  5. Indonesia 94 MW
  6. Finland 90 MW
  7. Australia 57 MW
  8. Norway 55 MW
  9. Portugal 40 MW
  10. Iceland 7 MW

Epoch AI covered the United States first and is adding sites in other countries, so the share of the tracked sites is not the share of the world. Epoch AI marks the owner of 4 sites as unconfirmed (VNET Bayin Ulanqab, QTS Cedar Rapids, Goodnight, QTS Eagle Mountain); each has its own bar here.

56% of the world’s arrived AI compute is outside Epoch AI’s tracked campuses

arrivals to 30 Jun 2026 · owners to 31 Dec 2025 · CSV

Epoch AI counts 27.4M H100-equivalents arrived worldwide by 30 Jun 2026. Its tracked campuses held 12.1M of them that day, 44%. The other 15.3M are at sites Epoch AI does not track.

By country, 30 Jun 2026

Arrived, Epoch AI's chip imports At the tracked campuses

  1. United States54 campuses 9.1M outof 19.7M
  2. China4 campuses 2.5M outof 2.7M
  3. European Union2 campuses in Finland, Portugal 1.3M outof 1.4M
  4. Malaysia4 campuses −249Kmore at campuses
  5. United Kingdom1 campus 215K outof 339K
  6. Indonesia1 campus 134K outof 218K
  7. Norway1 campus 79K outof 130K
  8. Iceland1 campus 90K outof 96K
  9. 212 other destinationsno tracked campus 2.1M outof 2.1M

By chip owner, 31 Dec 2025

Held, Epoch AI's chip owners At the tracked campuses

  1. Google13 campuses 3.4M outof 5.0M
  2. Microsoft5 campuses 2.6M outof 3.4M
  3. All other owners 3.4Mnot mapped
  4. Amazon4 campuses 1.6M outof 2.4M
  5. Meta4 campuses 1.8M outof 2.3M
  6. China 1.2Mnot mapped
  7. Oracle2 campuses 849K outof 1.1M
  8. CoreWeave4 campuses 601K outof 832K
  9. China, smuggled (estimate) 662Knot mapped
  10. xAI3 campuses −11Kmore at campuses

Google holds the most compute outside the tracked campuses: 3.4M H100e of its 5.0M, on 31 Dec 2025. What the chip makers sell into data centers.

How: each figure is one of Epoch AI's estimates less another, both in H100e, on the same day. A campus's compute is read from its own timeline on that day. A campus counts for a chip owner only where Epoch AI's rows name the same company, and Epoch AI's SpaceXAI campuses count as xAI. 961K H100e at 12 campuses are not mapped to an owner: Undisclosed 501K, ByteDance 221K, ByteDance (unconfirmed) 123K, Huawei 55K, Nebius 25K, Core42 20K, Alibaba 16K. All other owners, China and smuggled chips have no campus Epoch AI names, so they show the whole only. In Malaysia the campuses hold more than Epoch AI counts as arrived: the two estimates come from different runs and disagree there. xAI's campuses hold more than its owner estimate, so it shows no untracked part. The owners file ends earlier, so its dates differ from the arrivals. Epoch AI states its tracked sites hold 44% of world compute (30% to 78%), from a third file. These are modelled estimates, not an inventory.

US data-center building rises 90% in a year, to $96.5 bn a year

Construction spending, with every revision

U.S. Census Bureau, Construction Spending, release of 2 November 2026, public domain. Buildings only, without the servers inside. September 2026 is Census’s preliminary estimate, and the next two releases will revise it. The level, the change on a year earlier and the revisions.

All 96 sites

Download CSV
Site Owner Where Today Projected peak
Colossus 2 SpaceXAI Memphis, Tennessee 1.3 GW 2.1 GW · Feb 2027
Anthropic-Amazon New Carlisle Amazon New Carlisle, Indiana 1.2 GW 2.3 GW · Mar 2028
OpenAI Stargate Abilene Oracle Abilene, Texas 1.2 GW —
Microsoft Fairwater Atlanta Microsoft Fayetteville, Georgia 859 MW —
DayOne Nusajaya Undisclosed Johor Bahru, Johor, Malaysia 662 MW —
Meta Prometheus Meta New Albany, Ohio 612 MW 1.3 GW · Jul 2028
DayOne Kempas Undisclosed Kempas, Johor, Malaysia 590 MW —
Microsoft Fairwater Wisconsin Microsoft Mount Pleasant, Wisconsin 442 MW 2.7 GW · May 2028
Google Pryor (North) Google Pryor, Oklahoma 442 MW —
Colossus 1 SpaceXAI Memphis, Tennessee 425 MW —
Google New Albany Google New Albany, Ohio 400 MW —
CoreWeave Denton TX CoreWeave Denton, Texas 367 MW 395 MW · May 2027
Google Columbus Google Columbus, Ohio 364 MW 464 MW · Jul 2027
Amazon Madison Mega Site Amazon Canton, Mississippi 341 MW 819 MW · Mar 2028
QTS Richmond 1 Undisclosed Sandston, Virginia 333 MW —
Bridge Data Centres MY06 ByteDance Kulai, Johor, Malaysia 315 MW —
Google Bristow Google Bristow, Virginia 286 MW —
Google Omaha Google Omaha, Nebraska 284 MW 474 MW · Jul 2028
Google Council Bluffs (East) Google Council Bluffs, Iowa 284 MW —
Google Papillion Google Papillion, Nebraska 284 MW —
Amazon Ridgeland Amazon Ridgeland, Mississippi 273 MW 1.0 GW · Sep 2028
Microsoft Goodyear Microsoft Goodyear, Arizona 263 MW —
Huawei Wuhu Huawei Wuhu, Anhui, China 256 MW 589 MW · Dec 2027
AWS New Albany Amazon New Albany, Ohio 255 MW 405 MW · Jul 2027
VNET Bayin Ulanqab ByteDance (unconfirmed) Ulanqab, Inner Mongolia, China 252 MW 798 MW · Sep 2027
QTS Richmond 2 Undisclosed Sandston, Virginia 252 MW —
Anthropic Lake Mariner AI XPV Platform Barker, New York 245 MW 441 MW · Mar 2027
Meta-QTS Hillsboro 2 Meta Hillsboro, Oregon 243 MW —
Meta Jeffersonville Meta Jeffersonville, Indiana 241 MW —
Meta Rosemount Meta Rosemount, Minnesota 241 MW —
Google Mesa Google Mesa, Arizona 237 MW —
Meta Temple Meta Temple, Texas 231 MW —
Microsoft Project Osmium Microsoft Cumming, Iowa 228 MW —
Google Storey County Google Clark, Nevada 214 MW 389 MW · Jun 2027
Huawei Horinger Huawei Hohhot, Inner Mongolia, China 212 MW 439 MW · Feb 2028
Alibaba Zhangbei Alibaba Zhangbei, Hebei, China 203 MW —
QTS Richmond 3 Undisclosed Sandston, Virginia 202 MW 336 MW · Feb 2027
Coreweave Helios CoreWeave Afton, Texas 200 MW 800 MW · Jan 2029
Meta Montgomery Meta Montgomery, Alabama 199 MW 465 MW · Feb 2027
Meta Huntsville Meta Huntsville, Alabama 198 MW —
Meta Kuna Meta Kuna, Idaho 198 MW —
Google The Dalles Google The Dalles, Oregon 185 MW —
Meta Cheyenne Meta Cheyenne, Wyoming 182 MW 249 MW · Feb 2027
Meta Eagle Mountain Meta Eagle Mountain, Utah 179 MW —
Google Lincoln Google Lincoln, Nebraska 170 MW 339 MW · Oct 2027
Meta Aiken Meta Aiken, South Carolina 168 MW —
Google Lancaster Google Lancaster, Ohio 164 MW —
YTL Johor Undisclosed Kulai, Johor, Malaysia 155 MW 389 MW · Aug 2028
Envision Galaxy Ulanqab Undisclosed Ulanqab, Inner Mongolia, China 153 MW 612 MW · Dec 2027
Meta Los Lunas Meta Los Lunas, New Mexico 147 MW 273 MW · Jan 2028
AWS Berwick Amazon Berwick, Pennsylvania 139 MW 212 MW · Aug 2027
Google Kansas City East Google Kansas City, Missouri 126 MW —
Google Waltham Cross Google Cheshunt, Hertfordshire, United Kingdom 124 MW —
Google Midlothian Google Midlothian, Texas 123 MW —
STACK Infrastructure NVA02 Undisclosed Manassas, Virginia 118 MW 487 MW · Jan 2028
CoreWeave Chester VA CoreWeave Chester, Virginia 114 MW 197 MW · Jun 2027
Meta Gallatin Meta Gallatin, Tennessee 114 MW —
Microsoft SAT40 Microsoft San Antonio, Texas 106 MW —
Meta Sarpy Meta Springfield, Nebraska 105 MW —
Oracle Batam Oracle Batam, Riau Islands, Indonesia 94 MW —
Google Red Oak Google Red Oak, Texas 93 MW 185 MW · Dec 2026
Google Arcola Google Arcola, Virginia 93 MW —
CoreWeave Marble NC CoreWeave Marble, North Carolina 91 MW —
Nebius Mantsala Nebius Mantsala, Uusimaa, Finland 90 MW 196 MW · Dec 2027
CoreWeave Ellendale ND CoreWeave Ellendale, North Dakota 88 MW 520 MW · Jun 2027
Stream Phoenix Undisclosed Goodyear, Arizona 77 MW 267 MW · Jan 2030
Microsoft-Nebius New Jersey Nebius Vineland, New Jersey 70 MW —
Microsoft SAT14 Microsoft San Antonio, Texas 66 MW —
Core42 Lake Mariner Core42 Barker, New York 58 MW —
Southgate Melbourne Firmus Melbourne, Victoria, Australia 57 MW —
CoreWeave Norway CoreWeave Øvrebø, Agder, Norway 55 MW —
Vantage TX1 Undisclosed San Antonio, Texas 45 MW 179 MW · Aug 2027
Start Campus Sines Data Campus Nscale Sines, Setúbal, Portugal 40 MW 280 MW · Sep 2027
CoreWeave Dalton 1 & 2 CoreWeave Dalton, Georgia 40 MW —
xAI QTS Atlanta SpaceXAI Atlanta, Georgia 24 MW —
Nscale Keflavik Nscale Reykjanesbær, Suðurnes, Iceland 7 MW 13 MW · Dec 2026
OpenAI Stargate New Mexico Oracle Santa Teresa, New Mexico Building 2.5 GW · Dec 2028
Meta Hyperion Meta Holly Ridge, Louisiana Building 2.2 GW · Jan 2028
OpenAI Stargate Shackelford Oracle Abilene, Texas Building 2.0 GW · Nov 2028
QTS Cedar Rapids Meta (unconfirmed) Cedar Rapids, Iowa Building 1.6 GW · Nov 2027
OpenAI Stargate UAE G42 Abu Dhabi, Abu Dhabi, United Arab Emirates Building 1.4 GW · Jan 2028
OpenAI Stargate Michigan Oracle Benton, Michigan Building 1.4 GW · Dec 2028
OpenAI Stargate Wisconsin Oracle Port Washington, Wisconsin Building 1.3 GW · Dec 2028
Goodnight Google (unconfirmed) Claude, Texas Building 1.3 GW · Oct 2027
OpenAI Stargate Milam Softbank Burlington, Texas Building 1.2 GW · Dec 2028
Google Fort Wayne Google Fort Wayne, Indiana Building 1.0 GW · Jun 2028
Crusoe Abilene Expansion Microsoft Abilene, Texas Building 941 MW · Nov 2027
Meta Bowling Green Meta Bowling Green, Ohio Building 570 MW · Jan 2028
QTS Eagle Mountain Meta (unconfirmed) Eagle Mountain, Utah Building 411 MW · Jul 2027
Google Cedar Rapids Google Cedar Rapids, Iowa Building 314 MW · May 2027
Anthropic Barber Lake Cipher Mining Colorado City, Texas Building 300 MW · Apr 2027
OpenAI Stargate Lordstown Softbank Lordstown, Ohio Building 300 MW · Mar 2027
CoreWeave Muskogee OK CoreWeave Muskogee, Oklahoma Building 181 MW · Dec 2027
CoreWeave Lancaster Greenfield site CoreWeave Lancaster, Pennsylvania Building 124 MW · Jun 2027
Microsoft Narvik Norway Nscale Bjerkvik, Narvik, Norway Building 124 MW · Dec 2026
EcoDataCenter 2 Mistral AI Borlänge, Dalarna County, Sweden Building 67 MW · Jun 2028