Microsoft · San Antonio, Texas
Microsoft SAT14
66MW
The power of 54,000 US homes.
Drawing power since Jul 2024.
- H100-equivalents
- 45K
- Capital cost
- $1.8B
- Chips
- H100, B300
Power over time
facility power · 5 milestonesEvery milestone
- 18 Feb 2022 — Land clearing for the site is almost complete. Informed using imagery on Google Earth
- 1 Jul 2024 26 MW Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.
- 3 Aug 2025 26 MW Building 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.
- 28 Feb 2026 26 MW No more visible construction around either building, just a little equipment. Roads fully built around buildings as well.
- 31 Mar 2026 66 MW Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.
Gas made 40% of the power on this site's grid
net generation by fuel · Oct 2025 to Sep 2026Electric Reliability Council of Texas, Inc. ERCO · balancing authority
- Gas 40%
- Coal 12%
- Nuclear 8%
- Wind 24%
- Solar 16%
- Hydro <1%
- Other <1%
The grid of the utilities that serve Bexar County, TX. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.
Owners plan 750 MW of new power in Bexar County, mostly storage
power plants in Bexar County · EIA-860M, September 2026- Alamo City ESS
- Rush ESS
- Padua 3
- El Patrimonio
In service in Bexar County today: 5.0 GW. Since January 2023: 511 MW added, 942 MW retired. Owners plan to retire 1.5 GW more. A plant in the same county does not mean it feeds the site. Power plants near every AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of San Antonio. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.