Undisclosed · Kulai, Johor, Malaysia

YTL Johor

155MW

At full load, the power of 130,000 US homes.

Drawing power since Nov 2025. Projected to reach 389 MW by Aug 2028.

Capital cost
$4.3B
Chips
B200, B300, Rubin
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

On a light page, end the frame’s address with ?theme=light. Preview it light.

Cite
Download
Post on X
YTL Johor on a globe of the large AI data centers Epoch AI tracks.

Power over time

facility power · 6 milestones
Every milestone
  1. 1 Nov 2023 — Land clearing begins for Building 1.
  2. 3 Nov 2025 26 MW Building 1 is operational with Nvidia GB200s, according to the local investment development authority.
  3. 14 Mar 2026 138 MW Building 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this video. Solar panels are also being installed to the north west of the campus.
  4. 15 May 2026 155 MW Building 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).
  5. 13 Jul 2026 155 MW Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.
  6. 1 Aug 2028 · projected 389 MW Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per Kenanga via The Star; JDC4 phases Sep-25/Sep-26/Sep-27 per MIDF. The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park (Kenanga, 9 Dec 2024).

Coal made 43% of the power in Malaysia

share of generation · Jun 2025 to May 2026

Malaysia World

  1. Gas 34% against 21% for World
  2. Coal 43% against 33% for World
  3. Other fossil 1% against 3% for World
  4. Nuclear 0% against 9% for World
  5. Wind 0% against 9% for World
  6. Solar 2% against 10% for World
  7. Hydro 17% against 14% for World
  8. Bio & other 3% against 2% for World

Fossil 78% (+1 pt on a year earlier) · nuclear 0% · renewables 22% · 637 g CO2e per kWh, life cycle · Jun 2025 to May 2026. Generation for all of Malaysia, without imports; the data does not show which grid feeds the site. Every country behind an AI site.

Sources

selected by Epoch AI
  1. Official YTL page for the campus
  2. YTL press release on the use of GB200's
  3. Aerial footage including the campus

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 13 Nov 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Kulai. Grid: Ember, “Monthly Electricity Data and Yearly Electricity Data”, CC BY 4.0, retrieved 11 Oct 2026; shares computed here. All sources.