Meta Montgomery
199MW
The power of 160,000 US homes.
Drawing power since Jun 2026. Projected to reach 465 MW by Feb 2027.
- H100-equivalents
- 175K
- Capital cost
- $5.8B
- Chips
- B300
- Users
- Meta
Power over time
facility power · 6 milestonesEvery milestone
- 1 Mar 2024 — Land clearing begins.
- 4 Jul 2025 — Building 1 and 2 under construction, with all chillers visible.
- 20 Mar 2026 — Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.
- 18 Jun 2026 199 MW We estimate Buildings 1 and 2 are operational.
- 2 Feb 2027 · projected 266 MW Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.
- 23 Feb 2027 · projected 465 MW Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.
Epoch’s release of 2 Sep 2026 planned 2 steps here; 266 MW for Jan 2027 is 31 days later, projected. Planned against reached
Gas made 49% of the power on this site's grid
net generation by fuel · Oct 2025 to Sep 2026Southern Company Services, Inc. - Trans SOCO · balancing authority
- Gas 49%
- Coal 18%
- Nuclear 25%
- Wind 0%
- Solar 5%
- Hydro 2%
- Other 1%
The grid of the utilities that serve Montgomery County, AL. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.
Owners plan 80 MW of new power in Montgomery County, all solar
power plants in Montgomery County · EIA-860M, September 2026- SR Hope Hull
In service in Montgomery County today: 180 MW. Since January 2023: 180 MW added, 0 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Montgomery. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.