Meta · Huntsville, Alabama

Meta Huntsville

198MW

The power of 160,000 US homes.

Drawing power since Mar 2026.

Capital cost
$5.5B
Chips
B300
Users
Meta
Energy
Tennessee Valley Authority, NextEra Energy Resources, First Solar
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Meta Huntsville on a globe of the world's largest AI data centers.

Power over time

facility power · 6 milestones
Every milestone
  1. 13 Dec 2021 — Building 1 land clearing begins.
  2. 3 Mar 2025 — Building 2 roof starts to go on and its cooling installation is in progress.
  3. 4 Nov 2025 — We believe Building 1 and 2 are still being finished due to continued construction vehicles and unfinished land around the data center sites.
  4. 2 Feb 2026 — Color artifacts appear on small number of Building 1 fans. Continued presence of construction equipment and unfinished land around Building 2 suggests the final phase of construction.
  5. 4 Mar 2026 105 MW We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.
  6. 2 Jun 2026 198 MW We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.

Nuclear made 41% of the power on this site's grid

net generation by fuel · Oct 2025 to Sep 2026

Tennessee Valley Authority TVA · balancing authority

  1. Gas 33%
  2. Coal 16%
  3. Nuclear 41%
  4. Wind 0%
  5. Solar 2%
  6. Hydro 7%
  7. Other <1%

The grid of the utilities that serve Madison County, AL. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.

No new plant is planned in Madison County

power plants in Madison County · EIA-860M, September 2026

In service in Madison County today: 43 MW. Since January 2023: 32 MW added, 0 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.

Sources

selected by Epoch AI
  1. Announcement of expansion completing in 2026
  2. TVA solar installation announcements

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Huntsville. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.