Undisclosed · Ulanqab, Inner Mongolia, China

Envision Galaxy Ulanqab

612MW projected

The power of 500,000 US homes, once built.

Under construction. Projected to draw 612 MW by Dec 2027.

Chips
Ascend 950PR, Ascend 950DT
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Envision Galaxy Ulanqab on a globe of the world's largest AI data centers.

Power over time

facility power · 7 milestones
Every milestone
  1. 1 Aug 2025 — Land clearing begins for Building 1.
  2. 11 May 2026 — Building 2 is under construction.
  3. 6 Aug 2026 — Building 1 being commissioned, Building 3 under construction
  4. 5 Sep 2026 — Land clearing begins for Building 4.
  5. 1 Nov 2026 · projected 153 MW Building 1 expected to be fully operational, assuming a 3-month fit-out period
  6. 1 Jul 2027 · projected 306 MW Building 2 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning, as demonstrated by Building 1. Similarly. Building 3 is expected to be commissioned now.
  7. 1 Dec 2027 · projected 612 MW Building 4 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning as demonstrated by Building 1.

Coal made 54% of the power in China

share of generation · Sep 2025 to Aug 2026

China World

  1. Gas 3% against 21% for World
  2. Coal 54% against 33% for World
  3. Other fossil 1% against 3% for World
  4. Nuclear 5% against 9% for World
  5. Wind 11% against 9% for World
  6. Solar 12% against 10% for World
  7. Hydro 13% against 14% for World
  8. Bio & other 1% against 2% for World

Fossil 58% (−2 pts on a year earlier) · nuclear 5% · renewables 37% · 554 g CO2e per kWh, life cycle · Sep 2025 to Aug 2026. Generation for all of China, without imports; the data does not show which grid feeds the site. Every country behind an AI site.

Sources

selected by Epoch AI
  1. Envision Galaxy Campus website
  2. Interview with Envision’s head of AI data centers

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Ulanqab. Grid: Ember, “Monthly Electricity Data and Yearly Electricity Data”, CC BY 4.0, retrieved 11 Oct 2026; shares computed here. All sources.