Buildout · planned against reached

8 of 91 planned campus power increases have slipped or shrunk

Both the plan and the newest figure are Epoch AI’s estimates, from satellite images, permits and company statements. Plans from the releases of 2 Sep 2026 and 2 Oct 2026, held to the release retrieved 22 Oct 2026.

Embed

The frame credits Epoch AI and links back to its page. Preview it.

Cite
CSV Post on X

91 planned steps at 52 campuses, 30.9 GW of facility power

each step judged on the newest release
On plan
83 steps · 27.9 GW planned · at the planned size on the planned date
Later
6 steps · 711 MW planned · the planned size, on a later date
Smaller
2 steps · 2.3 GW planned · never at the planned size

6 steps slipped up to 167 days; 2 steps shrank 74 MW

planned date against the newest release
  1. Meta Prometheus 1.0 GW → 1.1 GW · planned Jan 2027 167 days later, projected
  2. Meta Prometheus 931 MW → 1.0 GW · planned Oct 2026 167 days later, projected
  3. Meta Prometheus 731 MW → 931 MW · planned Oct 2026 106 days later, projected
  4. Goodnight 0 MW → 133 MW · planned Dec 2026 90 days later, projected
  5. Goodnight 133 MW → 265 MW · planned Feb 2027 89 days later, projected
  6. Meta Montgomery 199 MW → 266 MW · planned Jan 2027 31 days later, projected
  7. Meta Hyperion 0 MW → 2.3 GW · planned Jan 2028 59 MW smaller
  8. Meta Cheyenne 182 MW → 264 MW · planned Feb 2027 15 MW smaller
planned date, first kept release newest release, projected newest release, recorded newest release, 22 Oct 2026

4 planned steps came due by 22 Oct 2026, and 3 arrived on time

steps whose planned date has passed
Campus Planned Planned power Newest, that day Outcome
Meta Prometheus 1 Oct 2026 931 MW 612 MW 106 days later, projected
DayOne Nusajaya 2 Oct 2026 662 MW 662 MW on time
Anthropic-Amazon New Carlisle 19 Oct 2026 1.2 GW 1.2 GW on time
Meta Temple 30 Sep 2026 231 MW 231 MW on time

Every planned step

91 steps · newest release, retrieved 22 Oct 2026
Every step as a table
Campus Planned on For Power Newest release Outcome
Meta PrometheusMeta 2 Sep 2026 28 Jan 2027 1.0 GW → 1.1 GW 14 Jul 2027 Later167 days later, projected
Meta PrometheusMeta 2 Sep 2026 30 Oct 2026 931 MW → 1.0 GW 15 Apr 2027 Later167 days later, projected
Meta PrometheusMeta 2 Sep 2026 1 Oct 2026 731 MW → 931 MW 15 Jan 2027 Later106 days later, projected
GoodnightGoogle 2 Sep 2026 15 Dec 2026 0 MW → 133 MW 15 Mar 2027 Later90 days later, projected
GoodnightGoogle 2 Sep 2026 15 Feb 2027 133 MW → 265 MW 15 May 2027 Later89 days later, projected
Meta MontgomeryMeta 2 Sep 2026 2 Jan 2027 199 MW → 266 MW 2 Feb 2027 Later31 days later, projected
Meta HyperionMeta 2 Sep 2026 1 Jan 2028 0 MW → 2.3 GW peak 2.2 GW Smaller59 MW smaller
Meta CheyenneMeta 2 Sep 2026 15 Feb 2027 182 MW → 264 MW peak 249 MW Smaller15 MW smaller
OpenAI Stargate New MexicoOracle 2 Sep 2026 31 Dec 2028 0 MW → 2.5 GW 31 Dec 2028 On planstill planned for this date
Microsoft Fairwater WisconsinMicrosoft 2 Sep 2026 13 May 2028 885 MW → 2.7 GW 13 May 2028 On planstill planned for this date
OpenAI Stargate MichiganOracle 2 Sep 2026 31 Dec 2028 0 MW → 1.4 GW 31 Dec 2028 On planstill planned for this date
OpenAI Stargate WisconsinOracle 2 Sep 2026 31 Dec 2028 0 MW → 1.3 GW 31 Dec 2028 On planstill planned for this date
OpenAI Stargate MilamSoftbank 2 Sep 2026 31 Dec 2028 0 MW → 1.2 GW 31 Dec 2028 On planstill planned for this date
OpenAI Stargate UAEG42 2 Sep 2026 1 Jan 2028 280 MW → 1.4 GW 1 Jan 2028 On planstill planned for this date
Anthropic-Amazon New CarlisleAmazon 2 Sep 2026 17 Mar 2028 1.2 GW → 2.3 GW 17 Mar 2028 On planstill planned for this date
GoodnightGoogle 2 Sep 2026 1 Oct 2027 265 MW → 1.3 GW 1 Oct 2027 On planstill planned for this date
QTS Cedar RapidsUndisclosed 2 Sep 2026 15 Nov 2027 627 MW → 1.6 GW 15 Nov 2027 On planstill planned for this date
Colossus 2SpaceXAI 2 Sep 2026 25 Feb 2027 1.3 GW → 2.1 GW 25 Feb 2027 On planstill planned for this date
Amazon RidgelandAmazon 2 Sep 2026 29 Sep 2028 341 MW → 1.0 GW 29 Sep 2028 On planstill planned for this date
QTS Cedar RapidsUndisclosed 2 Sep 2026 15 Nov 2026 0 MW → 627 MW 15 Nov 2026 On planstill planned for this date
OpenAI Stargate AbileneOracle 2 Sep 2026 1 Nov 2026 590 MW → 1.2 GW 1 Nov 2026 On planstill planned for this date
VNET Bayin UlanqabVNET 2 Sep 2026 1 Sep 2027 252 MW → 798 MW 1 Sep 2027 On planstill planned for this date
Crusoe Abilene ExpansionMicrosoft 2 Sep 2026 11 Nov 2027 470 MW → 941 MW 11 Nov 2027 On planstill planned for this date
Crusoe Abilene ExpansionMicrosoft 2 Sep 2026 17 Sep 2027 0 MW → 470 MW 17 Sep 2027 On planstill planned for this date
Microsoft Fairwater WisconsinMicrosoft 2 Sep 2026 20 Feb 2027 442 MW → 885 MW 20 Feb 2027 On planstill planned for this date
CoreWeave Ellendale NDCoreWeave 2 Sep 2026 1 Jun 2027 114 MW → 520 MW 1 Jun 2027 On planstill planned for this date
Coreweave HeliosCoreWeave 2 Sep 2026 1 Jan 2028 200 MW → 600 MW 1 Jan 2028 On planstill planned for this date
STACK Infrastructure NVA02Undisclosed 2 Sep 2026 1 Jan 2028 118 MW → 487 MW 1 Jan 2028 On planstill planned for this date
Meta Bowling GreenMeta 2 Oct 2026 1 Jan 2028 220 MW → 570 MW 1 Jan 2028 On planstill planned for this date
Amazon Madison Mega SiteAmazon 2 Sep 2026 15 Mar 2028 478 MW → 819 MW 15 Mar 2028 On planstill planned for this date
DayOne NusajayaUndisclosed 2 Sep 2026 2 Oct 2026 336 MW → 662 MW 2 Oct 2026 On planon time
OpenAI Stargate LordstownSoftbank 2 Sep 2026 1 Mar 2027 0 MW → 300 MW 1 Mar 2027 On planstill planned for this date
OpenAI Stargate UAEG42 2 Sep 2026 1 Dec 2026 0 MW → 280 MW 1 Dec 2026 On planstill planned for this date
QTS Eagle MountainMeta 2 Sep 2026 31 Dec 2026 0 MW → 274 MW 31 Dec 2026 On planstill planned for this date
Anthropic Barber LakeCipher Mining 2 Sep 2026 30 Dec 2026 0 MW → 244 MW 30 Dec 2026 On planstill planned for this date
Start Campus Sines Data CampusNscale 2 Sep 2026 30 Sep 2027 40 MW → 280 MW 30 Sep 2027 On planstill planned for this date
Google Fort WayneGoogle 2 Sep 2026 1 Dec 2026 0 MW → 207 MW 1 Dec 2026 On planstill planned for this date
Google Fort WayneGoogle 2 Sep 2026 31 Mar 2027 207 MW → 414 MW 31 Mar 2027 On planstill planned for this date
Google Fort WayneGoogle 2 Sep 2026 28 Aug 2027 414 MW → 621 MW 28 Aug 2027 On planstill planned for this date
Google Fort WayneGoogle 2 Sep 2026 25 Jan 2028 621 MW → 828 MW 25 Jan 2028 On planstill planned for this date
Google Fort WayneGoogle 2 Sep 2026 23 Jun 2028 828 MW → 1.0 GW 23 Jun 2028 On planstill planned for this date
Coreweave HeliosCoreWeave 2 Sep 2026 1 Jan 2029 600 MW → 800 MW 1 Jan 2029 On planstill planned for this date
Meta MontgomeryMeta 2 Sep 2026 23 Feb 2027 266 MW → 465 MW 23 Feb 2027 On planstill planned for this date
Anthropic Lake MarinerAI XPV Platform 2 Sep 2026 31 Oct 2026 49 MW → 245 MW 31 Oct 2026 On planstill planned for this date
Anthropic Lake MarinerAI XPV Platform 2 Sep 2026 31 Mar 2027 245 MW → 441 MW 31 Mar 2027 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 15 Aug 2027 0 MW → 196 MW 15 Aug 2027 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 19 Oct 2027 196 MW → 392 MW 19 Oct 2027 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 18 Nov 2027 392 MW → 588 MW 18 Nov 2027 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 11 Feb 2028 588 MW → 784 MW 11 Feb 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 8 Mar 2028 784 MW → 980 MW 8 Mar 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 4 Apr 2028 980 MW → 1.2 GW 4 Apr 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 12 May 2028 1.2 GW → 1.4 GW 12 May 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 17 Oct 2028 1.4 GW → 1.6 GW 17 Oct 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 18 Oct 2028 1.6 GW → 1.8 GW 18 Oct 2028 On planstill planned for this date
OpenAI Stargate ShackelfordOracle 2 Sep 2026 11 Nov 2028 1.8 GW → 2.0 GW 11 Nov 2028 On planstill planned for this date
Huawei WuhuHuawei 2 Oct 2026 31 Dec 2026 229 MW → 419 MW 31 Dec 2026 On planstill planned for this date
Stream PhoenixUndisclosed 2 Sep 2026 1 Jan 2030 77 MW → 267 MW 1 Jan 2030 On planstill planned for this date
Google Storey CountyGoogle 2 Sep 2026 30 Jun 2027 214 MW → 389 MW 30 Jun 2027 On planstill planned for this date
Google LincolnGoogle 2 Sep 2026 1 Oct 2027 170 MW → 339 MW 1 Oct 2027 On planstill planned for this date
Anthropic-Amazon New CarlisleAmazon 2 Sep 2026 19 Oct 2026 1.1 GW → 1.2 GW 19 Oct 2026 On planon time
AWS New AlbanyAmazon 2 Sep 2026 1 Jul 2027 255 MW → 405 MW 1 Jul 2027 On planstill planned for this date
Amazon Madison Mega SiteAmazon 2 Sep 2026 1 Mar 2027 341 MW → 478 MW 1 Mar 2027 On planstill planned for this date
QTS Eagle MountainMeta 2 Sep 2026 1 Jul 2027 274 MW → 411 MW 1 Jul 2027 On planstill planned for this date
Vantage TX1Undisclosed 2 Sep 2026 31 Aug 2027 45 MW → 179 MW 31 Aug 2027 On planstill planned for this date
QTS Richmond 3Undisclosed 2 Sep 2026 13 Feb 2027 202 MW → 336 MW 13 Feb 2027 On planstill planned for this date
CoreWeave Lancaster Greenfield siteCoreWeave 2 Oct 2026 30 Jun 2027 0 MW → 124 MW 30 Jun 2027 On planstill planned for this date
Microsoft Narvik NorwayNscale 2 Sep 2026 31 Dec 2026 0 MW → 124 MW 31 Dec 2026 On planstill planned for this date
Meta Bowling GreenMeta 2 Oct 2026 1 Feb 2027 0 MW → 117 MW 1 Feb 2027 On planstill planned for this date
Huawei WuhuHuawei 2 Oct 2026 1 Dec 2027 419 MW → 526 MW 1 Dec 2027 On planstill planned for this date
Nebius MantsalaNebius 2 Oct 2026 31 Dec 2027 90 MW → 196 MW 31 Dec 2027 On planstill planned for this date
Google Cedar RapidsGoogle 2 Sep 2026 31 Dec 2026 0 MW → 105 MW 31 Dec 2026 On planstill planned for this date
Google Cedar RapidsGoogle 2 Sep 2026 23 May 2027 209 MW → 314 MW 23 May 2027 On planstill planned for this date
Google Cedar RapidsGoogle 2 Sep 2026 22 Feb 2027 105 MW → 209 MW 22 Feb 2027 On planstill planned for this date
Meta Bowling GreenMeta 2 Oct 2026 1 Apr 2027 117 MW → 220 MW 1 Apr 2027 On planstill planned for this date
Google ColumbusGoogle 2 Sep 2026 1 Jul 2027 364 MW → 464 MW 1 Jul 2027 On planstill planned for this date
CoreWeave Muskogee OKCoreWeave 2 Sep 2026 31 Dec 2026 0 MW → 98 MW 31 Dec 2026 On planstill planned for this date
Google OmahaGoogle 2 Sep 2026 23 Jan 2028 284 MW → 379 MW 23 Jan 2028 On planstill planned for this date
Google OmahaGoogle 2 Sep 2026 23 Jul 2028 379 MW → 474 MW 23 Jul 2028 On planstill planned for this date
Google Red OakGoogle 2 Sep 2026 1 Dec 2026 93 MW → 185 MW 1 Dec 2026 On planstill planned for this date
CoreWeave Chester VACoreWeave 2 Sep 2026 30 Jun 2027 114 MW → 197 MW 30 Jun 2027 On planstill planned for this date
CoreWeave Muskogee OKCoreWeave 2 Sep 2026 31 Dec 2027 98 MW → 181 MW 31 Dec 2027 On planstill planned for this date
AWS BerwickAmazon 2 Sep 2026 1 Aug 2027 139 MW → 212 MW 1 Aug 2027 On planstill planned for this date
Amazon RidgelandAmazon 2 Sep 2026 9 Feb 2027 273 MW → 341 MW 9 Feb 2027 On planstill planned for this date
Anthropic Barber LakeCipher Mining 2 Sep 2026 30 Apr 2027 244 MW → 300 MW 30 Apr 2027 On planstill planned for this date
Huawei WuhuHuawei 2 Oct 2026 1 Nov 2026 181 MW → 229 MW 1 Nov 2026 On planstill planned for this date
EcoDataCenter 2Mistral AI 2 Oct 2026 30 Jun 2027 0 MW → 34 MW 30 Jun 2027 On planstill planned for this date
EcoDataCenter 2Mistral AI 2 Oct 2026 30 Jun 2028 34 MW → 67 MW 30 Jun 2028 On planstill planned for this date
Meta TempleMeta 2 Sep 2026 30 Sep 2026 198 MW → 231 MW 30 Sep 2026 On planon time
CoreWeave Denton TXCoreWeave 2 Sep 2026 31 May 2027 367 MW → 395 MW 31 May 2027 On planstill planned for this date
CoreWeave Ellendale NDCoreWeave 2 Sep 2026 31 Dec 2026 88 MW → 114 MW 31 Dec 2026 On planstill planned for this date
Nscale KeflavikNscale 2 Oct 2026 31 Dec 2026 7 MW → 13 MW 31 Dec 2026 On planstill planned for this date
  • Epoch AI, AI data centers, retrieved 22 Oct 2026, CC BY 4.0.
  • Earlier releases kept by this site: 2 Sep 2026 · 2 Oct 2026 · 11 Oct 2026 (the link is an Internet Archive copy).