Meta · Eagle Mountain, Utah
QTS Eagle Mountain
411MW projected
The power of 330,000 US homes, once built.
Under construction. Projected to draw 411 MW by Jul 2027.
- Chips
- B300
- Users
- Meta (unconfirmed)
Power over time
facility power · 5 milestonesEvery milestone
- 1 Oct 2023 — First signs of site preparation show up on satellite imagery.
- 8 Sep 2025 — Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.
- 2 May 2026 — Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.
- 31 Dec 2026 · projected 274 MW We estimate Buildings 1 and 2 will be fully operational by the end of 2026 because there are at least seven months since cooling and emergency generators have started to be installed. This estimate is also in line with similar QTS data center campus construction timelines.
- 1 Jul 2027 · projected 411 MW We estimate Building 3 will be fully operational by H2 2027 following a similar time line to Buildings 1 and 2 of 14 months from land clearing to operational.
Every step Epoch planned here on 2 Sep 2026 is still on plan. Planned against reached
Coal made 40% of the power on this site's grid
net generation by fuel · Oct 2025 to Sep 2026PacifiCorp - East PACE · balancing authority
- Gas 17%
- Coal 40%
- Nuclear 0%
- Wind 26%
- Solar 14%
- Hydro 2%
- Other 2%
The grid of the utilities that serve Utah County, UT. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.
No new plant is planned in Utah County
power plants in Utah County · EIA-860M, September 2026In service in Utah County today: 2.2 GW. Since January 2023: 697 MW added, 17 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Eagle Mountain. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.