ByteDance · Kulai, Johor, Malaysia
Bridge Data Centres MY06
315MW
The power of 260,000 US homes.
Drawing power since Dec 2022.
- H100-equivalents
- 221K
- Capital cost
- $9.2B
- Chips
- A100, H100, B200
- Users
- ByteDance
Power over time
facility power · 10 milestonesEvery milestone
- 1 Oct 2021 — Land clearing begins for campus 1, seen via satellite imagery. This start date is corroborated by the Malaysian Investment Development Authority, citing November for officially first breaking ground.
- 31 Dec 2022 25 MW Building 1 (MY06-1) is operational. The SEC filing for Chindata and local news sources reported the building was in service as of October 20, but only a subsequent filing confirmed 19 MW was utilized by December 31, so we conservatively assume December 31.
- 1 Mar 2023 25 MW Drone footage indicates that Building 1 is operating at full capacity, with 4 of 5 cooling tower fans spinning. Building 2 has 2 of 21 fans spinning and some ongoing construction work, so we assume it's not fully operational yet. We estimate another 3 months until full utilization.
- 30 May 2023 79 MW Building 2 (MY06-2) is operational.
- 5 Nov 2024 148 MW Building 3 and 4 are operational. Building 3 was originally scheduled for 2024Q4, and seemed partly operational in June, so it's likely to be fully utilized by this date. Building 4 was scheduled for delivery starting 2024Q1, but it typically takes a few more months to fit out and reach full utilization, so we think it's only fully utilized by this date. At Campus 2, Buildings 5-7 and Building 9 are close to finishing construction while Buildings 8 and 10 shells are still under construction. The Campus 2 substation looks complete.
- 9 Feb 2025 148 MW Construction looks complete on Building 5, 6 and 7, but we allow 3 more months for fit-out and ramping before declaring them operational.
- 25 May 2025 315 MW Buildings 5-7 are operational.
- 23 Sep 2025 315 MW Buildings 8 and 9 look structurally complete. The remaining building, building 10, still has construction material around it and scaffolding on the roof, with cooling units yet to be installed.
- 3 Mar 2026 315 MW All cooling units are now installed on Building 10. Drone footage from the same month shows most cooling units operating for Buildings 5-7, but none (or very few) for Buildings 8-10. So we don't think Buildings 8-10 are operating significantly yet.
- 13 Sep 2026 315 MW No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars). So we still don't think Buildings 8-10 are utilized.
Coal made 43% of the power in Malaysia
share of generation · Jun 2025 to May 2026Malaysia World
- Gas 34% against 21% for World
- Coal 43% against 33% for World
- Other fossil 1% against 3% for World
- Nuclear 0% against 9% for World
- Wind 0% against 9% for World
- Solar 2% against 10% for World
- Hydro 17% against 14% for World
- Bio & other 3% against 2% for World
Fossil 78% (+1 pt on a year earlier) · nuclear 0% · renewables 22% · 637 g CO2e per kWh, life cycle · Jun 2025 to May 2026. Generation for all of Malaysia, without imports; the data does not show which grid feeds the site. Every country behind an AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Kulai. Grid: Ember, “Monthly Electricity Data and Yearly Electricity Data”, CC BY 4.0, retrieved 11 Oct 2026; shares computed here. All sources.