Meta · Springfield, Nebraska
Meta Sarpy
105MW
The power of 85,000 US homes.
Drawing power since Aug 2026.
- H100-equivalents
- 92K
- Capital cost
- $3.0B
- Chips
- B300
- Users
- Meta
Power over time
facility power · 3 milestonesEvery milestone
- 1 Aug 2024 — Building 1 grading underway.
- 4 May 2026 — Building 1 shell, electrical and cooling equipment looks complete, with minimal construction work, so we expect it to be operational within 3 months.
- 2 Aug 2026 105 MW Building 1 is operational (estimate).
Wind made 37% of the power on this site's grid
net generation by fuel · Oct 2025 to Sep 2026Southwest Power Pool SWPP · balancing authority
- Gas 27%
- Coal 26%
- Nuclear 5%
- Wind 37%
- Solar 2%
- Hydro 3%
- Other <1%
The grid of the utilities that serve Sarpy County, NE. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.
Owners plan 272 MW of new power in Sarpy County, all gas
power plants in Sarpy County · EIA-860M, September 2026- Turtle Creek
- Papillion Creek Wastewater
In service in Sarpy County today: 866 MW. Since January 2023: 528 MW added, 2 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Springfield. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.