Meta · Los Lunas, New Mexico

Meta Los Lunas

114MW

The power of 93,000 US homes.

Drawing power since Mar 2026. Projected to reach 273 MW by Jan 2028.

Capital cost
$3.3B
Chips
B300
Users
Meta
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Meta Los Lunas on a globe of the world's largest AI data centers.

Power over time

facility power · 5 milestones
Every milestone
  1. 24 Jul 2024 — Land clearing starts for new building.
  2. 1 Mar 2026 114 MW Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.
  3. 28 Jul 2026 114 MW Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.
  4. 26 Oct 2026 · projected 147 MW Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
  5. 1 Jan 2028 · projected 273 MW Building 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.

Wind made 37% of the power on this site's grid

net generation by fuel · Oct 2025 to Sep 2026

Public Service Company of New Mexico PNM · balancing authority

  1. Gas 19%
  2. Coal 13%
  3. Nuclear 0%
  4. Wind 37%
  5. Solar 30%
  6. Hydro <1%
  7. Other <1%

The grid of the utilities that serve Valencia County, NM. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.

Owners plan 208 MW of new power in Valencia County, mostly solar

power plants in Valencia County · EIA-860M, September 2026
  1. Star Light Energy Center Solar · 200 MW · Dec 2026 · being built · Star Light Energy Center
  2. Trigo Sol Solar CSG Solar · 5 MW · Jan 2027 · being built · Trigo Sol Solar
  3. USS Meadow Lake Solar Solar · 3 MW · Dec 2026 · being built · USS Meadow Lake Solar LLC

In service in Valencia County today: 621 MW. Since January 2023: 355 MW added, 0 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.

Sources

selected by Epoch AI
  1. Meta fact sheet
  2. Air quality permit for expansion
  3. Construction contractor page for the site

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Los Lunas. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.