Nebius · Vineland, New Jersey

Microsoft-Nebius New Jersey

70MW

The power of 57,000 US homes.

Drawing power since Apr 2026.

Capital cost
$1.9B
Chips
B300
Users
Microsoft
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Microsoft-Nebius New Jersey on a globe of the world's largest AI data centers.

Power over time

facility power · 4 milestones
Every milestone
  1. 31 May 2024 — Land clearing begins for northern two buildings (Building 1-2).
  2. 15 Dec 2025 — By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.
  3. 15 Apr 2026 70 MW High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 (SemiAnalysis); this April image is our first high-resolution confirmation that the cooling is in place.
  4. 12 Jul 2026 70 MW Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

Gas made 41% of the power on this site's grid

net generation by fuel · Oct 2025 to Sep 2026

PJM Interconnection, LLC PJM · balancing authority

  1. Gas 41%
  2. Coal 17%
  3. Nuclear 31%
  4. Wind 4%
  5. Solar 3%
  6. Hydro 2%
  7. Other 3%

The grid of the utilities that serve Cumberland County, NJ. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.

No new plant is planned in Cumberland County

power plants in Cumberland County · EIA-860M, September 2026

In service in Cumberland County today: 555 MW. Since January 2023: 17 MW added, 84 MW retired. Owners plan to retire 212 MW more. A plant in the same county does not mean it feeds the site. Power plants near every AI site.

Sources

selected by Epoch AI
  1. Nebius: up to 300 MW capacity at new New Jersey data center
  2. DataOne and Nebius partner for 300 MW AI data center (Data Centre Magazine)
  3. Microsoft secures 100,000 NVIDIA GB300 via Nebius deal (Tom's Hardware)
  4. DataOne CEO on first 50 MW delivery to Nebius (LinkedIn)
  5. Large data center nears completion in Vineland (Cape May County Herald)
  6. SemiAnalysis: Stop Saying Half of 2026 US Datacenter Capacity Is Canceled

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Vineland. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.