Oracle · Abilene, Texas
OpenAI Stargate Abilene
590MW
The power of 480,000 US homes.
Drawing power since Sep 2025. Projected to reach 1.2 GW by Nov 2026.
- H100-equivalents
- 509K
- Capital cost
- $16.0B
- Chips
- B200, B300
- Users
- OpenAI
- Project
- Stargate
- Energy
- American Electric Power
Power over time
facility power · 9 milestonesEvery milestone
- 31 May 2024 — Land clearing begins for northern two buildings (Building 1-2)
- 28 Jun 2025 — Building 1 looks close to finishing construction, with chillers in place. OpenAI stated that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenant improvement" work is not due until September, however.
- 26 Sep 2025 147 MW Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm that both buildings are fully operational. The announcement also stated that "Oracle began delivering the first NVIDIA GB200 racks in June", and we think 3 months is enough time to ram to 50,000 GB200s in Building 1. The satellite image also suggests that Building 1 is complete (shell and equipment done, many cars neatly parked) while Building 2 is ongoing (trucks and construction equipment still present). The 200 MW substation built in 2022 and expanded in 2024 is enough to power both buildings. To the right of Building 2, five gas turbines are in place with five more turbines still under construction. Chillers are partly installed for Building 3. Roof is complete for Building 4. The larger 1 GW substation is not complete yet.
- 24 Dec 2025 295 MW Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also consistent with satellite imagery. By January 15, Building 2 looked as finished as Building 1, whereas on September 26 it did not look finished.
- 15 Jan 2026 295 MW The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building 4 has about 80% of chillers installed. Other buildings have few or no chillers installed.
- 24 Mar 2026 295 MW Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete.
- 23 May 2026 590 MW Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.
- 28 Jul 2026 590 MW Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.
- 1 Nov 2026 · projected 1.2 GW Buildings 5-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24.
Every step Epoch planned here on 2 Sep 2026 is still on plan. Planned against reached
Gas made 40% of the power on this site's grid
net generation by fuel · Oct 2025 to Sep 2026Electric Reliability Council of Texas, Inc. ERCO · balancing authority
- Gas 40%
- Coal 12%
- Nuclear 8%
- Wind 24%
- Solar 16%
- Hydro <1%
- Other <1%
The grid of the utilities that serve Taylor County, TX. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.
Owners plan 299 MW of new power in Taylor County, all storage
power plants in Taylor County · EIA-860M, September 2026- Chimney Rock BESS
- Summerhill BESS
In service in Taylor County today: 991 MW. Since January 2023: 20 MW added, 0 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Abilene. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.