Google · Clark, Nevada

Google Storey County

214MW

The power of 170,000 US homes.

Drawing power since Aug 2023. Projected to reach 389 MW by Jun 2027.

Capital cost
$6.1B
Chips
TPU v5e, TPU v4, TPU v6e, TPU v5p
Users
Google DeepMind (unconfirmed)
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Google Storey County on a globe of the world's largest AI data centers.

Power over time

facility power · 6 milestones
Every milestone
  1. 30 Aug 2023 107 MW Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed.
  2. 11 Mar 2025 107 MW Building 2 now has generators in place, but there is still a crane and construction work present.
  3. 30 Jun 2025 214 MW Building 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front.
  4. 28 Sep 2025 214 MW Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped.
  5. 13 Apr 2026 214 MW Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.
  6. 30 Jun 2027 · projected 389 MW Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the number of generators reported in an air quality permit application (p.92-93). The dry cooler array is more than double the size of the Building 1 array, which suggests an even larger power capacity than we estimate, but we believe the generator-based estimate is more reliable here.

Every step Epoch planned here on 2 Sep 2026 is still on plan. Planned against reached

Gas made 57% of the power on this site's grid

net generation by fuel · Oct 2025 to Sep 2026

Nevada Power Company NEVP · balancing authority

  1. Gas 57%
  2. Coal 6%
  3. Nuclear 0%
  4. Wind 1%
  5. Solar 25%
  6. Hydro 1%
  7. Other 11%

The grid of the utilities that serve Storey County, NV. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.

Owners plan 1 MW of new power in Storey County, all solar

power plants in Storey County · EIA-860M, September 2026
  1. Tesla Reno GigaFactory Solar · 1 MW · Dec 2026 · being built · Tesla Inc.

In service in Storey County today: 1.2 GW. Since January 2023: 0 MW added, 0 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.

Sources

selected by Epoch AI
  1. Air quality permit application listing emergency generators and a small "R&D" fuel cell plant
  2. Aterio
  3. Google data center page

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Clark. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.