Huawei · Hohhot, Inner Mongolia, China
Huawei Horinger
212MW
The power of 170,000 US homes.
Drawing power since Jun 2025. Projected to reach 415 MW by Feb 2028.
- H100-equivalents
- 89K
- Capital cost
- $7.0B
- Chips
- Ascend 910C
Power over time
facility power · 12 milestonesEvery milestone
- 8 Oct 2023 — Land clearing begins simultaneously for all three campuses (west, north, and south) after an official ceremony. Two of the campuses later have the cooling capacity indicative of AI workloads, while the other (the north campus) does not.
- 24 Feb 2025 — On the west zone, building 1 is structurally complete, and building 4 is structurally complete apart from some remaining cooling towers. Buildings 2 and 5 have begun construction.
- 1 Apr 2025 — Four buildings are seen to be structurally complete via satellite imagery.
- 1 Jun 2025 42 MW On the west zone, building 1 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery.
- 1 Jul 2025 85 MW On the east zone, building 4 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery.
- 1 Feb 2026 131 MW On the west zone, building 2 is operational assuming a 3 month fit out post structural completion, as can be seen via satellite imagery.
- 5 Mar 2026 131 MW Three of the six buildings planned across the three campuses (what can be called phase 1) are operational. One other is near completion, apart from backup generators. The third campus does not have cooling sufficient for AI.
- 12 May 2026 131 MW Satellite imagery shows buildings 4 and 5 on the east zone are structurally complete, with landscaping complete.
- 7 Jun 2026 131 MW Satellite imagery shows buildings 1 and 2 on the west zone are structurally complete, with landscaping complete.
- 1 Jul 2026 212 MW On the east zone, building 5 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery.
- 18 Aug 2026 212 MW On the east zone, building 6 is under construction, and potentially larger than any of the identically sized buildings constructed thus far. Building 3 has not begun construction.
- 14 Feb 2028 · projected 415 MW Building 6 is operational (estimate). This was the only new building under construction as of August 2026. Buildings in the previous phases each took 1.6 to 2.3 years from laying the foundations to becoming operational. The new building has a similar shape to a new building at the Huawei Wuhu campus which, based on its cooling and backup power capacity, is about 3.7x the power of previous buildings (see calculations sheet). We expect the chips to be 910C, or to have about the same energy efficiency as the 910C.
Coal made 54% of the power in China
share of generation · Sep 2025 to Aug 2026China World
- Gas 3% against 21% for World
- Coal 54% against 33% for World
- Other fossil 1% against 3% for World
- Nuclear 5% against 9% for World
- Wind 11% against 9% for World
- Solar 12% against 10% for World
- Hydro 13% against 14% for World
- Bio & other 1% against 2% for World
Fossil 58% (−2 pts on a year earlier) · nuclear 5% · renewables 37% · 554 g CO2e per kWh, life cycle · Sep 2025 to Aug 2026. Generation for all of China, without imports; the data does not show which grid feeds the site. Every country behind an AI site.
Sources
selected by Epoch AIData: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Hohhot. Grid: Ember, “Monthly Electricity Data and Yearly Electricity Data”, CC BY 4.0, retrieved 11 Oct 2026; shares computed here. All sources.