Power · large-load tariffs

24 states have approved large-load power tariffs for data centers

30 tariffs and rules are approved, and 14 more are filed and waiting for a decision.

Each row is a utility’s schedule or a state rule for very large new loads such as data centers, filed or decided from Jan 2024 to Oct 2026, as the regulator or the utility states it.

Embed

The frame credits state regulators and the utilities’ own filings and links back to its page. Preview it.

Cite
CSV Post on X

Where a data-center tariff or rule is approved, filed or absent

every state

Montana, North Dakota, South Dakota, Colorado, Delaware and Oklahoma have only filings.

  1. AK
  2. ME
  3. WI 2
  4. VT
  5. NH
  6. WA
  7. ID
  8. MT 1
  9. ND 1
  10. MN 1
  11. IL 1
  12. MI 2
  13. NY
  14. MA
  15. OR 3
  16. NV
  17. WY
  18. SD 1
  19. IA
  20. IN 1
  21. OH 2
  22. PA 2
  23. NJ
  24. CT
  25. RI
  26. CA 1
  27. UT 1
  28. CO 1
  29. NE
  30. MO 3
  31. KY 6
  32. WV 1
  33. VA 2
  34. MD
  35. DE 1
  36. AZ 2
  37. NM
  38. KS 1
  39. AR
  40. TN 1
  41. NC 2
  42. SC 1
  43. DC
  44. OK 1
  45. LA
  46. MS 1
  47. AL 1
  48. GA 2
  49. HI
  50. TX 3
  51. FL 2
Approved Filed only None found Number on a tile: tariffs and rules approved or filed

14 of 16 minimum bills charge for at least 80% of reserved power

approved tariffs and rules · stated values only
Minimum bill, share of reserved demand
  1. 70% 1
  2. 75% 1
  3. 80% 12
  4. 90% 2

16 of 30 approved state it

Shortest contract term
  1. 5 yr 1
  2. 10 yr 2
  3. 12 yr 6
  4. 14 yr 1
  5. 15 yr 6
  6. 20 yr 2

18 of 30 approved state it

Size that brings a load under it
  1. 15 MW 1
  2. 20 MW 2
  3. 25 MW 3
  4. 40 MW 1
  5. 50 MW 6
  6. 70 MW 1
  7. 75 MW 4
  8. 100 MW 5
  9. 150 MW 1

24 of 30 approved state it

Contracts run 15 years or longer in 8 of 18 tariffs. Each large-load tariff sets its own mix: most also charge an exit fee and ask for collateral, and some admit only loads with a high load factor; the register shows which.

48% of US AI capacity sits where a large-load tariff applies

the sites
  • Approved tariff 7.3 GW · 48%
  • Tariff filed only 0.2 GW · 1%
  • No tariff found 7.8 GW · 51%
US AI capacity drawing power now, 15.3 GW at 60 sites

Matched through the utilities that EIA lists for each county; a county with several utilities counts when any one has a tariff. State rules and TVA’s wholesale rate are not matched to a site.

Site County Drawing now Large-load tariff
Colossus 2 Shelby County, TN 1,276 MW none found
Anthropic-Amazon New Carlisle St. Joseph County, IN 1,244 MW Indiana Michigan Power (I&M) · approved
Microsoft Fairwater Atlanta Fayette County, GA 859 MW Georgia Power · approved
Meta Prometheus Franklin County, OH 612 MW AEP Ohio (Ohio Power Company) · approved
OpenAI Stargate Abilene Taylor County, TX 590 MW none found
Google Pryor (North) Mayes County, OK 442 MW none found
Microsoft Fairwater Wisconsin Racine County, WI 442 MW We Energies (Wisconsin Electric Power Company) · approved
Colossus 1 Shelby County, TN 425 MW none found
Google New Albany Franklin County, OH 400 MW AEP Ohio (Ohio Power Company) · approved
CoreWeave Denton TX Denton County, TX 367 MW none found
Google Columbus Franklin County, OH 364 MW AEP Ohio (Ohio Power Company) · approved
Amazon Madison Mega Site Madison County, MS 341 MW none found
QTS Richmond 1 Henrico County, VA 333 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Google Bristow Prince William County, VA 286 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Google Council Bluffs (East) Pottawattamie County, IA 284 MW none found
Google Omaha Douglas County, NE 284 MW none found
Google Papillion Sarpy County, NE 284 MW none found
Amazon Ridgeland Madison County, MS 273 MW none found
Microsoft Goodyear Maricopa County, AZ 263 MW Arizona Public Service Company · filedSalt River Project · approved
AWS New Albany Franklin County, OH 255 MW AEP Ohio (Ohio Power Company) · approved
QTS Richmond 2 Henrico County, VA 252 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Meta-QTS Hillsboro 2 Washington County, OR 243 MW Portland General Electric Company · approved
Meta Jeffersonville Clark County, IN 241 MW none found
Meta Rosemount Dakota County, MN 241 MW Xcel Energy (Northern States Power Company - Minnesota) · approved
Google Mesa Maricopa County, AZ 237 MW Arizona Public Service Company · filedSalt River Project · approved
Meta Temple Bell County, TX 231 MW none found
Microsoft Project Osmium Warren County, IA 228 MW none found
Google Storey County Storey County, NV 214 MW none found
QTS Richmond 3 Henrico County, VA 202 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Coreweave Helios Dickens County, TX 200 MW none found
Meta Montgomery Montgomery County, AL 199 MW none found
Meta Huntsville Madison County, AL 198 MW none found
Meta Kuna Ada County, ID 198 MW none found
Google The Dalles Wasco County, OR 185 MW PacifiCorp, d/b/a Pacific Power · filedPacifiCorp dba Pacific Power · approved
Meta Cheyenne Laramie County, WY 182 MW none found
Meta Eagle Mountain Utah County, UT 179 MW none found
Google Lincoln Lancaster County, NE 170 MW none found
Google Lancaster Fairfield County, OH 164 MW AEP Ohio (Ohio Power Company) · approved
AWS Berwick Columbia County, PA 139 MW PPL Electric Utilities Corporation · approved
Google Kansas City East Jackson County, MO 126 MW Evergy Missouri Metro and Evergy Missouri West · approved
Google Midlothian Ellis County, TX 123 MW none found
STACK Infrastructure NVA02 Manassas city, VA 118 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
CoreWeave Chester VA Chesterfield County, VA 114 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Meta Gallatin Sumner County, TN 114 MW none found
Meta Los Lunas Valencia County, NM 114 MW none found
Microsoft SAT40 Bexar County, TX 106 MW none found
Meta Sarpy Sarpy County, NE 105 MW none found
Google Arcola Loudoun County, VA 93 MW Dominion Energy Virginia (Virginia Electric and Power Company) · approved
Google Red Oak Ellis County, TX 93 MW none found
CoreWeave Marble NC Cherokee County, NC 91 MW Duke Energy Carolinas and Duke Energy Progress · filed
Meta Aiken Aiken County, SC 90 MW none found
CoreWeave Ellendale ND Dickey County, ND 88 MW Otter Tail Power Company · filed
Stream Phoenix Maricopa County, AZ 77 MW Arizona Public Service Company · filedSalt River Project · approved
Microsoft-Nebius New Jersey Cumberland County, NJ 70 MW none found
Microsoft SAT14 Bexar County, TX 66 MW none found
Core42 Lake Mariner Niagara County, NY 58 MW none found
Anthropic Lake Mariner Niagara County, NY 49 MW none found
Vantage TX1 Bexar County, TX 45 MW none found
CoreWeave Dalton 1 & 2 Whitfield County, GA 40 MW Georgia Power · approved
xAI QTS Atlanta Fulton County, GA 24 MW Georgia Power · approved

Every tariff and rule

tariffs.csv
Date Tariff Status Threshold Minimum bill Term Exit fee · collateral Sources
Oct 2026 filed Duke Energy Carolinas and Duke Energy Progress · Large Load Tariff (service under Schedule HLF) NC · North Carolina Utilities Commission · E-7, Sub 1329; E-2, Sub 1380 Duke Energy and the NC Public Staff filed a settlement on a Large Load Tariff for loads of 50 MW or more with a high load factor; below 100 MW the minimum term is 10 years, and billing demand is at least 75% of contract demand. Filed 50 MW 75% 10 yr yes · yes Duke Energy, 7 October 2026 · news.duke-energy.comDuke Energy Carolinas and Duke Energy Progress (filing posted by SELC), 6 October 2026 · selc.org
Sep 2026 decided ERCOT transmission and distribution service providers · 16 TAC §25.194 Large Load Interconnection Standards TX · Public Utility Commission of Texas · Project No. 58481 · state rule The PUCT adopted a rule under SB 6 that makes new ERCOT loads of 75 MW or more post financial security of $50,000 per MW and sets the consequences of withdrawing requested demand. The decided date is the filing date of the adoption order. Approved 75 MW not stated not stated not stated · yes Public Utility Commission of Texas, 18 September 2026 · interchange.puc.texas.gov
Sep 2026 filed The Empire District Electric Company d/b/a Liberty · Transmission Service Large Load (TS-LL) tariff MO · Missouri Public Service Commission · ET-2026-0184 Liberty filed a proposed Transmission Service Large Load tariff with the Missouri PSC and asks for an order by January 31, 2027; the press release does not give the size threshold. Filed not stated not stated not stated not stated · not stated Missouri Public Service Commission, 17 September 2026 · psc.mo.gov
Aug 2026 decided Indiana Michigan Power (I&M) · Tariff LP (Large Power) Large Load Customer terms MI · Michigan Public Service Commission · U-21986 Michigan Large Load Customers of 50 MW or more sign an initial term of at least 15 years after a ramp of up to 5 years, are billed at least 90% of contract capacity, give collateral of 50% of the exit fee, and pay an exit fee to leave early. Approved 50 MW 90% 15 yr ramp up to 5 yr yes · yes Indiana Michigan Power, 18 September 2026 · indianamichiganpower.com
Aug 2026 decided Tennessee Valley Authority · Data center rate (wholesale rate structure change) TN, AL, MS, KY, GA, NC, VA · TVA Board of Directors The TVA Board created a new data center rate as part of changes to its wholesale rate structure; the release does not give the size threshold or contract terms. Approved not stated not stated not stated not stated · not stated Tennessee Valley Authority, 20 August 2026 · s205.q4cdn.com
Aug 2026 as of Xcel Energy (Public Service Company of Colorado) · Large Load Tariff CO · Colorado Public Utilities Commission · 26AL-0137E Xcel Energy asked the Colorado PUC to approve a large load tariff that makes customers of 50 MW or more pay for the transmission, substations and new generation needed to serve them. Filed 50 MW not stated not stated not stated · not stated Colorado Department of Regulatory Agencies (PUC Newsletter), 4 August 2026 · content.govdelivery.com
Jul 2026 filed Otter Tail Power Company · Large General Service - Tier III - High Power Compute SD · South Dakota Public Utilities Commission · EL26-021 Otter Tail Power proposed a High Power Compute rate for data center loads of at least 75 MW, a take-or-pay service with a 15-year minimum term after the buildout period, collateral and liquidated damages. Filed 75 MW not stated 15 yr yes · yes Otter Tail Power Company, 27 July 2026 · puc.sd.govOtter Tail Power Company, 27 July 2026 · puc.sd.gov
Jul 2026 filed AES Ohio (The Dayton Power and Light Company) · Data Center Tariff (in rate-plan settlement) OH · Public Utilities Commission of Ohio · 25-958-EL-AIR AES Ohio filed an unopposed rate-plan settlement that includes a new Data Center Tariff; it is pending before the PUCO. Filed not stated not stated not stated not stated · not stated AES Ohio, 21 July 2026 · aes-ohio.com
Jun 2026 filed Xcel Energy (Northern States Power Company-Wisconsin) · Large Load Customer General Time of Day Service Tariff WI · Public Service Commission of Wisconsin · 4220-TE-119 Proposed tariff for new loads of 100 MW or more with 15-year commitments, financial security, minimum monthly payments, and exit fees; pending before the Wisconsin PSC. Filed 100 MW not stated 15 yr yes · yes Xcel Energy, 22 June 2026 · wpr.orgPublic Service Commission of Wisconsin · apps.psc.wi.gov
Jun 2026 filed OG&E · Proposed large-load tariff OK · Oklahoma Corporation Commission OG&E filed a large-load tariff with the OCC for new loads of 75 MW or more, with a 15-year term, a ramp of up to five years, minimum bills and collateral. Filed 75 MW not stated 15 yr ramp up to 5 yr yes · yes OG&E, 18 June 2026 · oge.com
Jun 2026 filed Otter Tail Power Company · Large General Service - Tier III - High Power Compute ND · North Dakota Public Service Commission · PU-26-215 Otter Tail Power proposed a High Power Compute rate for data center loads of at least 75 MW, a take-or-pay service with a 15-year minimum term after the buildout period, collateral and liquidated damages. Filed 75 MW not stated 15 yr yes · yes Otter Tail Power Company, 18 June 2026 · psc.nd.gov
Jun 2026 decided PPL Electric Utilities Corporation · Rate Schedule LP-6 Large Load Interconnections PA · Pennsylvania Public Utility Commission · R-2025-3057164 Data center customers of 50 MW or more sign an agreement of at least 10 years with a ramp of up to 5 years, pay on at least 80% of their ramp-schedule load, post security equal to upgrade costs, and owe an exit fee. Approved 50 MW 80% 10 yr ramp up to 5 yr yes · yes PPL Electric Utilities, 30 June 2026 · pplelectric.comPennsylvania Public Utility Commission, 4 June 2026 · puc.pa.gov
May 2026 decided Xcel Energy (Northern States Power Company - Minnesota) · Very large customer tariff framework and customer class MN · Minnesota Public Utilities Commission · 25-289 A new very large customer class for new loads of 100 MW or more, with a 15-year default contract, a 24-month exit notice, and a minimum bill and exit fee set at 80% of contracted capacity. Approved 100 MW 80% 15 yr yes · not stated Minnesota Public Utilities Commission, 18 May 2026 · content.govdelivery.com
May 2026 decided Portland General Electric Company · Schedule 96 (large load data center class) OR · Public Utility Commission of Oregon · UM 2377 The Oregon PUC created Schedule 96 for PGE data centers, with minimum generation and transmission demand charges at 90 percent of contracted capacity, contract terms from 10 to 30 years by size, exit fees and collateral rules. Approved 20 MW 90% 10 yr yes · yes Public Utility Commission of Oregon, 7 May 2026 · apps.puc.state.or.usPublic Utility Commission of Oregon · oregon.gov
Apr 2026 decided Pennsylvania electric distribution companies (model tariff) · Model Tariff for Customers at or over 50 MW Individually or 100 MW in the Aggregate (Large Load Customer) PA · Pennsylvania Public Utility Commission · M-2025-3054271 · state rule A statewide model tariff (guidance, not a utility schedule) for loads of 50 MW or 100 MW aggregated: initial term of at least 5 years after a 3-to-5-year ramp, 80% minimum demand charge, collateral to cover upgrade costs, and an exit fee. Approved 50 MW 80% 5 yr ramp up to 5 yr yes · yes Pennsylvania Public Utility Commission, 30 April 2026 · puc.pa.govPennsylvania Public Utility Commission, 12 May 2026 · puc.pa.gov
Apr 2026 decided We Energies (Wisconsin Electric Power Company) · Very Large Customer (VLC) and Bespoke Resources Tariffs WI · Public Service Commission of Wisconsin · 6630-TE-113 The Commission approved a modified Very Large Customer tariff for loads of 100 MW or more with a minimum initial term of 15 years and a requirement that these customers pay 100% of their resource costs. Approved 100 MW not stated 15 yr not stated · not stated Public Service Commission of Wisconsin, 24 April 2026 · psc.wi.gov
Apr 2026 filed Duke Energy Florida, LLC · Large Load Customer Policy (LLCP) and Large Load Customer Agreement (LLCA) FL · Florida Public Service Commission · 20260064-EI Duke Energy Florida filed a Large Load Customer Policy for loads of 50 MW or more with a 20-year term and a minimum demand of 75% to 85% of contract capacity; the case is pending. Filed 50 MW not stated 20 yr yes · yes Duke Energy Florida, LLC, 22 April 2026 · psc.state.fl.usFlorida Public Service Commission, 28 July 2026 · psc.state.fl.us
Apr 2026 filed El Paso Electric Company · Schedule No. 27 - High Load Factor Large Power Service Rate (HLFLP) TX · Public Utility Commission of Texas · 59611 El Paso Electric asked the PUCT to approve Schedule 27 for data center and advanced manufacturing loads of 75 MW or more, with a 20-year minimum term that includes the load ramp, security and termination damages. Filed 75 MW not stated 20 yr yes · yes El Paso Electric Company, 7 April 2026 · interchange.puc.texas.gov
Mar 2026 filed NorthWestern Energy (NorthWestern Corporation) · Large New Load Tariff MT · Montana Public Service Commission NorthWestern Energy asked the Montana PSC to approve a Large New Load Tariff for new or expanded loads of 5 MW or more, with collateral and termination costs. Filed 5 MW not stated not stated yes · yes NorthWestern Energy, 31 March 2026 · northwesternenergy.com
Mar 2026 as of ComEd (Commonwealth Edison Company) · Large load tariff changes adding deposit protection (Large Demand Project Applicants or Customers) IL · Illinois Commerce Commission · 25-0677/25-0679 (consolidated) The ICC approved ComEd tariff changes that add deposit protection if a large demand project such as a data center is canceled or abandoned, and the ICC must open an investigation of a large-load tariff. Approved ICC describes the requests as 50 MW or more; the tariff threshold itself is not stated in the press release not stated not stated not stated · yes Illinois Commerce Commission, 20 March 2026 · icc.illinois.gov
Feb 2026 decided Kentucky Utilities Company (KU) · Extremely High Load Factor (Rate EHLF) KY · Kentucky Public Service Commission · 2025-00113 New customers above 50 MVA with very high load factor sign an initial contract of at least 15 years, are billed at least 80% of contract capacity, give collateral, and pay an exit fee to leave early. Approved Contract capacity greater than 50 MVA (reduced from 100 MVA); new customers only; threshold is in MVA, not MW 80% 15 yr yes · yes Kentucky Public Service Commission, 16 February 2026 · psc.ky.govKentucky Public Service Commission · psc.ky.gov
Feb 2026 decided Louisville Gas and Electric Company (LG&E) · Extremely High Load Factor (Rate EHLF) KY · Kentucky Public Service Commission · 2025-00114 New LG&E customers above 50 MVA with very high load factor sign an initial contract of at least 15 years, are billed at least 80% of contract capacity, give collateral, and pay an exit fee to leave early. Approved Capacity greater than 50 MVA (reduced from 100 MVA); new customers only; threshold is in MVA, not MW 80% 15 yr yes · yes Kentucky Public Service Commission, 16 February 2026 · psc.ky.govKentucky Public Service Commission · psc.ky.gov
Jan 2026 decided Florida Power & Light Company · Large Load Contract Service (LLCS-1, LLCS-2 and LLCS Service Agreement) FL · Florida Public Service Commission · 20250011-EI The Florida PSC approved the FPL 2025 rate settlement, which includes the LLCS-1 and LLCS-2 large load rate schedules for new loads of 50 MW or more with a 70% take-or-pay demand charge. Approved 50 MW 70% 20 yr yes · yes Florida Public Service Commission staff, 14 November 2025 · psc.state.fl.usFlorida Power & Light Company, 13 February 2026 · psc.state.fl.usFlorida Power & Light Company, 10 November 2025 · psc.state.fl.us
Jan 2026 decided Rocky Mountain Power (PacifiCorp) and other qualified electric utilities · R746-318 Large Scale Electric Requirements UT · Public Service Commission of Utah · 25-R318-01 · state rule The Utah PSC made rule R746-318 effective on January 1, 2026; it directly assigns interconnection and transmission upgrade costs to large load customers and sets a 60-day review of large load contracts. Approved applies to large load customers as defined in Utah Code 54-26-101; no MW figure in the rule text not stated not stated not stated · not stated Public Service Commission of Utah, 15 January 2026 · pscdocs.utah.govPublic Service Commission of Utah, 31 October 2025 · pscdocs.utah.gov
Dec 2025 filed Delmarva Power & Light Company · Large load tariff (proposed revised tariff pages) DE · Delaware Public Service Commission · 25-0826 Delmarva filed a proposed large load tariff on Commission order for customers of 25 MW or more; the case is pending before the Delaware PSC. Filed 25 MW not stated not stated not stated · not stated Delaware Public Service Commission · depsc.delaware.gov
Nov 2025 decided Dominion Energy Virginia (Virginia Electric and Power Company) · Rate Schedule GS-5 VA · Virginia State Corporation Commission · PUR-2025-00058 A new GS-5 class, from January 1, 2027, for customers of 25 MW or more at 75% load factor, with a 14-year contract that includes a ramp of up to 4 years, minimum charges of 85% for distribution and transmission and 60% for generation, collateral, and an exit fee. Approved 25 MW not stated 14 yr ramp up to 4 yr yes · yes Virginia State Corporation Commission, 25 November 2025 · scc.virginia.govVirginia State Corporation Commission, 25 November 2025 · npr.brightspotcdn.com
Nov 2025 decided Ameren Missouri · Large Load Customer Service (Schedule LLCS) MO · Missouri Public Service Commission · ET-2025-0184 The Missouri PSC approved the Ameren Missouri large load rate plan (Schedule LLCS) for loads of 75 MW or more; the compliance tariff became effective on January 4, 2026. Approved 75 MW 80% 12 yr ramp up to 5 yr yes · yes Ameren Missouri, 24 November 2025 · ameren.mediaroom.comAmeren Missouri and signatories · efis.psc.mo.govAmeren Missouri, 14 May 2025 · efis.psc.mo.govMissouri Public Service Commission, 8 December 2025 · efis.psc.mo.govMissouri Public Service Commission, 19 December 2025 · efis.psc.mo.gov
Nov 2025 decided Evergy Missouri Metro and Evergy Missouri West · Large Load Power Service (Schedule LLPS) MO · Missouri Public Service Commission · EO-2025-0154 The Missouri PSC approved a non-unanimous settlement and authorized Evergy LLPS schedules for new or expanded loads of 75 MW; the compliance tariffs became effective on March 9, 2026. Approved 75 MW 80% 12 yr ramp up to 5 yr yes · yes Missouri Public Service Commission, 13 November 2025 · efis.psc.mo.govMissouri Public Service Commission, 25 February 2026 · efis.psc.mo.gov
Nov 2025 decided Consumers Energy · Rate GPD data center (large load) provision MI · Michigan Public Service Commission · U-21859 Data centers and other customers of 100 MW or more sign a contract of at least 15 years with a minimum billing demand of 80% paid whether used or not, may ramp over up to 5 years, and must give collateral and pay an exit fee to leave early. Approved 100 MW 80% 15 yr ramp up to 5 yr yes · yes Michigan Public Service Commission, 6 November 2025 · michigan.gov
Nov 2025 decided Evergy Kansas Central · Large Load Power Service (Schedule LLPS) KS · Kansas Corporation Commission · 25-EKME-315-TAR The KCC approved a settlement that sets a Large Load Power Service rate for new or expanded loads of 75 MW or more, with a 12-year term plus an optional ramp of up to 5 years. Approved 75 MW 80% 12 yr ramp up to 5 yr yes · yes Kansas Corporation Commission, 6 November 2025 · kcc.ks.govEvergy Kansas Central, 6 November 2025 · evergy.com
Oct 2025 decided East Kentucky Power Cooperative (with its owner-member cooperatives) · Data Center Power Tariff (Rate DCP) KY · Kentucky Public Service Commission · 2025-00140 Data centers of 15 MW or more at 60% load factor take service under Rate DCP through a Commission-approved special contract and must keep a prepayment deposit of two months of expected bills. Approved 15 MW not stated not stated not stated · yes Kentucky Public Service Commission, 30 October 2025 · psc.ky.govKentucky Public Service Commission · psc.ky.gov
Oct 2025 decided Duke Energy Kentucky · Financial assurance and minimum demand terms for high-volume Rate DT and Rate TT customers KY · Kentucky Public Service Commission · 2024-00354 New Rate DT and TT customers of 40 MW or more sign a service agreement with a minimum demand of 75% of their specified load and may have to give financial and credit assurance. Approved 40 MW 75% not stated not stated · not stated Kentucky Public Service Commission, 2 October 2025 · psc.ky.govKentucky Public Service Commission · psc.ky.gov
Oct 2025 filed PacifiCorp, d/b/a Pacific Power · Schedule 401 - Service to New Large Energy Use Facilities OR · Public Utility Commission of Oregon · UE 463 (Advice 25-015) Pacific Power proposed Schedule 401, a new class for data centers of 20 MW or more with a contract of 10 years or more; the Oregon PUC has not decided it. Filed 20 MW not stated 10 yr not stated · not stated PacifiCorp (Pacific Power), 2 October 2025 · edocs.puc.state.or.usPublic Utility Commission of Oregon · oregon.gov
Aug 2025 decided Appalachian Power Company and Wheeling Power Company · Schedule L.C.P. (Large Capacity Power Service) Large Load Customers provisions WV · Public Service Commission of West Virginia · 24-0854-E-42T New loads of 100 MW at one site (or 150 MW aggregated) sign an initial term of at least 12 years after a ramp of up to 5 years, are billed at least 80% of contract capacity, give collateral, and pay an exit fee to leave early. Approved 100 MW 80% 12 yr ramp up to 5 yr yes · yes Appalachian Power · appalachianpower.com
Jul 2025 decided El Paso Electric Company · Rate Schedule No. 33A - Large Economic Development Service Rate TX · Public Utility Commission of Texas · 56903 The PUCT approved El Paso Electric's Schedule 33A, an economic development rate for data center customers above 50,000 kW. Approved 50 MW not stated not stated not stated · not stated Public Utility Commission of Texas, 31 July 2025 · interchange.puc.texas.govEl Paso Electric Company, 7 April 2026 · interchange.puc.texas.govEl Paso Electric Company · epelectric.com
Jul 2025 decided Pacific Gas and Electric Company · Electric Rule 30 - Transmission-Level Retail Electric Service (interim) CA · California Public Utilities Commission · A.24-11-007 The CPUC approved an interim Electric Rule 30 for PG&E customers that take retail service at transmission level, such as AI data centers. Approved transmission-level customers at 50-230 kV; no MW threshold stated not stated not stated not stated · not stated California Public Utilities Commission, 24 July 2025 · docs.cpuc.ca.govCalifornia Public Utilities Commission, 24 July 2025 · docs.cpuc.ca.gov
Jul 2025 decided AEP Ohio (Ohio Power Company) · Data Center Tariff (Schedule DCT) OH · Public Utilities Commission of Ohio · 24-508-EL-ATA New data center customers of 25 MW or more pay a minimum demand that rises with their size and cannot exceed 85% of contract capacity, over a 12-year term that includes a 4-year ramp; they give collateral and pay an exit fee to leave early. Approved 25 MW not stated 12 yr ramp up to 4 yr yes · yes AEP Ohio · aepohio.comAmerican Electric Power, 9 July 2025 · aep.comPublic Utilities Commission of Ohio, 9 July 2025 · dam.assets.ohio.gov
Jun 2025 filed Arizona Public Service Company · Extra High Load Factor Rate Schedule XHLF (proposed changes) AZ · Arizona Corporation Commission · E-01345A-25-0105 In its 2025 rate case, APS proposed to make data centers take service on its XHLF rate; the Arizona Corporation Commission has not voted. Filed all data centers under the proposal; the current optional rate starts at 5,000 kW not stated not stated not stated · not stated Arizona Public Service Company, 13 June 2025 · s22.q4cdn.comArizona Corporation Commission, 10 July 2026 · azcc.govArizona Public Service Company · aps.com
Apr 2025 decided South Carolina Public Service Authority (Santee Cooper) · Experimental Large Load Service Schedule L-25-LL SC · Santee Cooper Board of Directors Santee Cooper adopted an experimental large load schedule for data centers above 50 MW, with no contract demand reduction before 15 years of service. Approved 50 MW not stated not stated not stated · not stated Santee Cooper, 25 April 2025 · santeecooper.com
Mar 2025 decided Kentucky Power Company · Industrial General Service Tariff (Tariff I.G.S.) large-load provisions KY · Kentucky Public Service Commission · 2024-00305 Customers adding 150 MW or more sign a 20-year contract, are billed at least 90% of their highest established demand, give collateral of 24 months of non-fuel bills, and pay five years of minimum bills if they close early. Approved 150 MW not stated 20 yr yes · yes Kentucky Public Service Commission, 18 March 2025 · psc.ky.govKentucky Public Service Commission · psc.ky.gov
Feb 2025 decided Salt River Project · E-67 Standard Price Plan for Large Load Substation Large General Service AZ · SRP Board of Directors The SRP board approved a revised E-67 price plan that new accounts of 20 MW or more must take, with a minimum billing demand of 80 percent of forecasted demand. Approved 20 MW 80% not stated not stated · not stated Salt River Project · srpnet.comSalt River Project, 27 February 2025 · srpnet.comSalt River Project, 2 December 2024 · srpnet.com
Feb 2025 decided Indiana Michigan Power (I&M) · Tariff I.P. (Industrial Power) Large Load Customer provisions IN · Indiana Utility Regulatory Commission · Cause No. 46097 Large Load Customers of 70 MW or more at one plant sign an initial term of at least 12 years with a ramp of up to 5 years, are billed at least 80% of contract capacity, give collateral and pay an exit fee to leave early. Approved 70 MW 80% 12 yr ramp up to 5 yr yes · yes Indiana Michigan Power · indianamichiganpower.comAmerican Electric Power, 19 February 2025 · aep.comAmerican Electric Power, 22 November 2024 · aep.com
Jan 2025 decided Georgia Power · Revisions to Rules and Regulations for Large Load customers (100 MW or more) GA · Georgia Public Service Commission · 44280 The Georgia PSC approved Georgia Power rule changes that let it apply special terms, longer contracts and minimum bills to new loads above 100 MW, and requires PSC review of each such contract. Approved 100 MW not stated not stated not stated · not stated Georgia Public Service Commission, 23 January 2025 · psc.ga.govGeorgia Public Service Commission Staff and Georgia Power, 26 August 2026 · services.psc.ga.gov
Dec 2024 decided PacifiCorp dba Pacific Power · Capacity reservation charge and excess demand charge for large load customers OR · Public Utility Commission of Oregon · UE 433 In Pacific Power's 2024 rate case, the Oregon PUC adopted a capacity reservation charge and an excess demand charge for customers above 25,000 kW. Approved 25 MW not stated not stated not stated · not stated Public Utility Commission of Oregon, 19 December 2024 · apps.puc.state.or.us
Not counted · 49 items

By state

30 states with a tariff or rule · the rest have none in the register
  • The orders, releases and docket pages of the state regulators and public power boards, and the utilities’ own releases, filings and tariff sheets: 78 documents, linked on each row above, checked 19 October 2026.
  • The utilities of each county: U.S. Energy Information Administration, Form EIA-861, as on the Power pages. The sites and what they draw: the Buildout.
  • Each row is a set of facts, with short quotations from its sources as evidence.