Power · large-load tariffs
24 states have approved large-load power tariffs for data centers
Each row is a utility’s schedule or a state rule for very large new loads such as data centers, filed or decided from Jan 2024 to Oct 2026, as the regulator or the utility states it.
- AK
- ME
- WI 2
- VT
- NH
- WA
- ID
- MT 1
- ND 1
- MN 1
- IL 1
- MI 2
- NY
- MA
- OR 3
- NV
- WY
- SD 1
- IA
- IN 1
- OH 2
- PA 2
- NJ
- CT
- RI
- CA 1
- UT 1
- CO 1
- NE
- MO 3
- KY 6
- WV 1
- VA 2
- MD
- DE 1
- AZ 2
- NM
- KS 1
- AR
- TN 1
- NC 2
- SC 1
- DC
- OK 1
- LA
- MS 1
- AL 1
- GA 2
- HI
- TX 3
- FL 2
48% of US AI capacity sits where a large-load tariff applies
- Approved tariff 7.3 GW · 48%
- Tariff filed only 0.2 GW · 1%
- No tariff found 7.8 GW · 51%