Companies · 5 datasets

Meta

$30.1B of capital spending in Q2 2026, 17 AI campuses drawing 2.9 GW and computing with 2.5M H100-equivalents now, 5 nuclear agreements, 1 frontier model.

Embed

The frame credits Epoch AI, Company filings, The parties’ releases and LMArena and links back to its page. Preview it.

Cite
CSV Post on X

$30.1B of capital spending in Q2 2026, up 82% on a year earlier

Every company's capex →
  1. Q3 2024 $8.3B of capital spending
  2. Q4 2024 $14.4B of capital spending
  3. Q1 2025 $12.9B of capital spending
  4. Q2 2025 $16.5B of capital spending
  5. Q3 2025 $18.8B of capital spending
  6. Q4 2025 $21.4B of capital spending
  7. Q1 2026 $19.0B of capital spending
  8. Q2 2026 $30.1B of capital spending

Purchases of property and equipment (Meta's headline capex also adds principal payments on finance leases), from the company's filings, in US dollars. The last four quarters total $89.3B.

Meta’s AI campuses draw 2.9 GW now, 7.4 GW at planned peak

The Buildout →
Campus Role Power now H100e now Planned peak First power
Meta PrometheusNew Albany, Ohio, United States owner and user 612 MW 536K 1.3 GWJul 2028 Oct 2025
Meta-QTS Hillsboro 2Hillsboro, Oregon, United States owner and user 243 MW 124K 243 MWNov 2024 Aug 2023
Meta JeffersonvilleJeffersonville, Indiana, United States owner and user 241 MW 203K 241 MWJun 2026 Jun 2026
Meta RosemountRosemount, Minnesota, United States owner and user 241 MW 216K 241 MWJun 2026 Jun 2026
Meta TempleTemple, Texas, United States owner and user 231 MW 202K 231 MWSep 2026 Dec 2025
Meta MontgomeryMontgomery, Alabama, United States owner and user 199 MW 175K 465 MWFeb 2027 Jun 2026
Meta HuntsvilleHuntsville, Alabama, United States owner and user 198 MW 167K 198 MWJun 2026 Mar 2026
Meta KunaKuna, Idaho, United States owner and user 198 MW 173K 198 MWJun 2026 Jun 2026
Meta CheyenneCheyenne, Wyoming, United States owner and user 182 MW 173K 249 MWFeb 2027 Jul 2026
Meta Eagle MountainEagle Mountain, Utah, United States owner and user 179 MW 151K 179 MWDec 2025 Dec 2025
Meta Los LunasLos Lunas, New Mexico, United States owner and user 114 MW 100K 273 MWJan 2028 Mar 2026
Meta GallatinGallatin, Tennessee, United States owner and user 114 MW 100K 114 MWAug 2026 Aug 2026
Meta SarpySpringfield, Nebraska, United States owner and user 105 MW 92K 105 MWAug 2026 Aug 2026
Meta AikenAiken, South Carolina, United States owner and user 90 MW 78K 168 MWNov 2026 Aug 2026
Meta HyperionHolly Ridge, Louisiana, United States owner and user — — 2.2 GWJan 2028 Jan 2028
Meta Bowling GreenBowling Green, Ohio, United States owner and user — — 570 MWJan 2028 Feb 2027
QTS Eagle MountainEagle Mountain, Utah, United States owner and user — — 411 MWJul 2027 Dec 2026

Owner and users as Epoch AI names them. The totals above count the campuses Meta owns, not those it uses.

7 AI supercomputers in Epoch AI’s list to Jul 2025, 158,118 H100-equivalents operating then

Every listed supercomputer →
Cluster Country H100e Status From
Meta 100k United States 100,000 existing (likely) Oct 2024
Meta GenAI 2024a United States 24,576 existing Mar 2024
Meta GenAI 2024b United States 24,576 existing Mar 2024
Meta Research SuperCluster (RSC-1) Phase 2 United States 5,045 existing May 2023
Meta Research SuperCluster 2 (RSC-2) United States 2,522 existing Oct 2023
Meta 2017 V100 Cluster United States 1,390 existing Oct 2017
Meta 2017 P100 Cluster United States 9 existing Jun 2017

Epoch AI stopped this list in Jul 2025; the H100-equivalents now at each campus are in the campus table above, and on the Machine’s compute layer.

5 nuclear agreements, 3.7 GW under contract and 4.0 GW in frameworks

Every agreement →
AnnouncedAgreementStatedStatus
Jan 2026 Oklo campus, Pike Countywith Oklo 1,200 MW framework
Jan 2026 Up to eight Natrium plantswith TerraPower 2,800 MW framework
Jan 2026 Perry and Davis-Bessewith Vistra 2,176 MW contract
Jan 2026 Uprates at Perry, Davis-Besse and Beaver Valleywith Vistra 433 MW contract
Jun 2025 Clintonwith Constellation 1,121 MW contract

1 model that led or matched the top of an LMArena board

Frontier →
  1. llama-3.1-405b-instruct first seen Jul 2024 0 days in first place

Days in first place, summed across LMArena's boards.