Power · large loads waiting for the grid
467.4 GW of large loads ask to join ERCOT’s grid by 2033
That is 5.1 times the 91,134 MW peak demand that ERCOT called an unofficial record in July 2026. These are requests to connect, not plants being built. ERCOT counts each load at the size its customer asked for, adds the years up, and prints the queue each month in its operational overview to its Board. ERCOT names no project, so this page joins no data center to the queue. Retrieved 3 November 2026.
The queue grew from 136.6 GW to 467.4 GW in 16 monthly overviews
the whole queue, by the last year each table showsEach bar is the whole queue in one overview: ERCOT’s tables add the years up, so the last year holds every request. The tables run to 2030 until February 2026, and to 2033 from March 2026. ERCOT’s overviews for August 2026 and September 2026 print no queue table, so July 2026 is the newest.
ERCOT’s peak demand, for scale: “ERCOT set a new unofficial all-time peak demand record of 91,134 MW” (ERCOT Monthly Operational Overview (July 2026)).
52% of the queue is “No Studies Submitted”
July 2026 · ERCOT’s status words · by 2033| Project status | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| No Studies Submitted | 0.0 | 0.0 | 0.0 | 4.1 | 32.3 | 101.0 | 180.6 | 221.1 | 233.1 | 244.6 | 244.9 | 244.9 |
| Under ERCOT Review | 0.0 | 0.0 | 0.0 | 3.0 | 9.9 | 44.5 | 94.0 | 114.1 | 126.5 | 132.0 | 132.0 | 132.0 |
| Section 9.4 Requirements Only | 0.0 | 0.0 | 0.0 | 0.0 | 1.7 | 6.6 | 10.9 | 13.4 | 13.8 | 13.8 | 13.8 | 13.8 |
| Section 9.4/9.5 Requirements Met | 0.0 | 0.0 | 0.0 | 0.0 | 13.6 | 42.0 | 56.2 | 60.3 | 63.8 | 66.8 | 67.2 | 67.2 |
| A2E but not operational | 0.0 | 0.4 | 1.8 | 3.2 | 3.7 | 3.7 | 3.7 | 3.7 | 3.7 | 3.7 | 3.7 | 3.7 |
| Observed Energized | 3.3 | 4.3 | 4.8 | 5.7 | 5.7 | 5.7 | 5.7 | 5.7 | 5.7 | 5.7 | 5.7 | 5.7 |
| Total | 3.3 | 4.7 | 6.6 | 16.0 | 66.9 | 203.5 | 351.2 | 418.4 | 446.8 | 466.8 | 467.4 | 467.4 |
ERCOT defines each status on the slide itself: ERCOT Monthly Operational Overview (July 2026), p. 9.
4,370 MW of large load is drawing power, of 9,456 MW approved to energize
what ERCOT observes, July 2026“Of the 9,456 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous monthly peak consumption of 4,370 MW in July 2026.”
ERCOT, ERCOT Monthly Operational Overview (July 2026). The peak is the sum of each approved load’s highest draw in the month, so the loads did not all draw it at once.
Sources
queue.csv Every dataset → Status → Glossary →- ERCOT, ERCOT Monthly Operational Overview (April 2025), 15 May 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (May 2025), 17 June 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (June 2025), 17 July 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (July 2025), 15 August 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (August 2025), 22 September 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (September 2025), 17 October 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (October 2025), 17 November 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (November 2025), 16 December 2025, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (December 2025), 15 January 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (January 2026), 18 February 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (February 2026), 18 March 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (March 2026), 16 April 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (April 2026), 19 May 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (May 2026), 15 June 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (June 2026), 17 July 2026, p. 9.
- ERCOT, ERCOT Monthly Operational Overview (July 2026), 17 August 2026, p. 9.
- The overviews for February 2025, March 2025, August 2026, September 2026 have no queue slide.
- ERCOT’s terms of use allow its public contents to be reproduced unmodified. This site keeps each table image as ERCOT embedded it, with its sha256, in the CSV.