Power · large loads waiting for the grid

467.4 GW of large loads ask to join ERCOT’s grid by 2033

That is 5.1 times the 91,134 MW peak demand that ERCOT called an unofficial record in July 2026. These are requests to connect, not plants being built. ERCOT counts each load at the size its customer asked for, adds the years up, and prints the queue each month in its operational overview to its Board. ERCOT names no project, so this page joins no data center to the queue. Retrieved 3 November 2026.

Embed

The frame credits ERCOT and links back to its page. Preview it.

Cite
CSV Post on X

The queue grew from 136.6 GW to 467.4 GW in 16 monthly overviews

the whole queue, by the last year each table shows
  1. Apr 2025 by 2030 136.6 GW of large load in the queue
  2. May 2025 by 2030 156.1 GW of large load in the queue
  3. Jun 2025 by 2030 172.8 GW of large load in the queue
  4. Jul 2025 by 2030 188.2 GW of large load in the queue
  5. Aug 2025 by 2030 189.3 GW of large load in the queue
  6. Sep 2025 by 2030 205.4 GW of large load in the queue
  7. Oct 2025 by 2030 223.5 GW of large load in the queue
  8. Nov 2025 by 2030 230.8 GW of large load in the queue
  9. Dec 2025 by 2030 233.6 GW of large load in the queue
  10. Jan 2026 by 2030 237.2 GW of large load in the queue
  11. Feb 2026 by 2030 238.6 GW of large load in the queue
  12. Mar 2026 by 2033 429.8 GW of large load in the queue
  13. Apr 2026 by 2033 438.1 GW of large load in the queue
  14. May 2026 by 2033 474.7 GW of large load in the queue
  15. Jun 2026 by 2033 465.5 GW of large load in the queue
  16. Jul 2026 by 2033 467.4 GW of large load in the queue

Each bar is the whole queue in one overview: ERCOT’s tables add the years up, so the last year holds every request. The tables run to 2030 until February 2026, and to 2033 from March 2026. ERCOT’s overviews for August 2026 and September 2026 print no queue table, so July 2026 is the newest.

ERCOT’s peak demand, for scale: “ERCOT set a new unofficial all-time peak demand record of 91,134 MW” (ERCOT Monthly Operational Overview (July 2026)).

52% of the queue is “No Studies Submitted”

July 2026 · ERCOT’s status words · by 2033
  1. Observed Energized 5.7 GW of large load by 2033
  2. A2E but not operational 3.7 GW of large load by 2033
  3. Section 9.4/9.5 Requirements Met 67.2 GW of large load by 2033
  4. Section 9.4 Requirements Only 13.8 GW of large load by 2033
  5. Under ERCOT Review 132.0 GW of large load by 2033
  6. No Studies Submitted 244.9 GW of large load by 2033
ERCOT’s table, July 2026, in GW, each year adding to the last
Project status 202220232024202520262027202820292030203120322033
No Studies Submitted 0.00.00.04.132.3101.0180.6221.1233.1244.6244.9244.9
Under ERCOT Review 0.00.00.03.09.944.594.0114.1126.5132.0132.0132.0
Section 9.4 Requirements Only 0.00.00.00.01.76.610.913.413.813.813.813.8
Section 9.4/9.5 Requirements Met 0.00.00.00.013.642.056.260.363.866.867.267.2
A2E but not operational 0.00.41.83.23.73.73.73.73.73.73.73.7
Observed Energized 3.34.34.85.75.75.75.75.75.75.75.75.7
Total 3.34.76.616.066.9203.5351.2418.4446.8466.8467.4467.4

ERCOT defines each status on the slide itself: ERCOT Monthly Operational Overview (July 2026), p. 9.

4,370 MW of large load is drawing power, of 9,456 MW approved to energize

what ERCOT observes, July 2026

“Of the 9,456 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous monthly peak consumption of 4,370 MW in July 2026.”

ERCOT, ERCOT Monthly Operational Overview (July 2026). The peak is the sum of each approved load’s highest draw in the month, so the loads did not all draw it at once.